Tariffs drive up costs for Centennial project

Nearly $12 million rise blamed on Trump steel policy

- By Art Marroquin Las Vegas Review-journal

The cost of building the next phase of the Centennial Bowl in northwest Las Vegas skyrockete­d by nearly $12 million from original estimates, primarily driven by President Donald Trump’s steel tariffs, the Nevada Department of Transporta­tion said Monday.

The department’s board of directors awarded a $61.5 million contract to Las Vegas Paving, a significan­t leap from the agency’s original estimate of $49 million to $59 million for a project that calls for building the next three freeway ramps linking U.S. Highway 95 and the 215 Beltway.

Constructi­on could start in late December for the next phase of the Centennial Bowl, which will rely on 5.2 million pounds of structural and reinforcin­g steel, accounting for about $5.3 million of the project’s total, NDOT officials said.

“As you can imagine, ending up with a bid on a project like this

that was 25 percent higher than what our engineers estimated can cause quite a bit of excitement,” Cole Mortensen, NDOT’S assistant director of engineerin­g, told the board on Monday.

The bridges are “packed full of reinforcin­g steel as well as pre

BOWL

stressing steel, and the falsework is steel, too,” Mortensen said. “All those things tend to add to an increase in cost for the project.”

Other factors help drive up the constructi­on costs, Mortensen said.

To meet a compressed constructi­on deadline of spring 2020, work will need to be completed simultaneo­usly on a pair of flyover bridges planned for the Centennial Bowl, Mortensen said. As a result, Las Vegas Paving will need to double the amount of steel supports — known as falsework — to frame the constructi­on project.

“It’s important to make a record as to why we’re taking the action that we’re taking so that anyone who looks back on this can understand why the contract amount was

$12 million more than what the estimate was,” said Gov. Brian Sandoval, who chairs the NDOT board.

Also, a gas line runs near the freeway interchang­e, which Mortensen said may have caused some constructi­on contractor­s to “shy away” from bidding on the massive project.

Las Vegas Paving submitted the sole bid, NDOT spokesman Tony

Illia said. Aggregate Industries, Fisher Sand & Gravel, Meadow Valley Contractor­s and Security Paving Co. also showed interest.

“It doesn’t do anybody any good to rebid a job because all the numbers are exposed,” NDOT board member Len Savage said just before voting in favor of the constructi­on contract.

Constructi­on of the Centennial Bowl began in August 2015, and the initial phase was completed in 2016 with the opening of a ramp linking northbound U.S. 95 to the eastbound Beltway. A half-mile span connecting the westbound Beltway and southbound U.S. 95 opened in July 2017.

Work will resume by the end of this year for the next phase of the Centennial Bowl, which calls for building a flyover ramp carrying vehicles from northbound U.S. 95 to the westbound Beltway, a second flyover ramp connecting the southbound U.S. 95 to the eastbound Beltway and a surface-level ramp linking the eastbound Beltway to southbound U.S. 95.

 ?? Michael Quine ?? Las Vegas Review-journal @Vegas88s An aerial view shows the 215 Beltway transition overpass to U.S. Highway 95 South on Monday.
Michael Quine Las Vegas Review-journal @Vegas88s An aerial view shows the 215 Beltway transition overpass to U.S. Highway 95 South on Monday.

Newspapers in English

Newspapers from United States