Las Vegas Review-Journal

Several milestones left for stadium

Roof cable installati­on to start in September

- By Mick Akers Las Vegas Review-journal

Now that constructi­on crews have placed the last steel beam connecting a ring of roof trusses on the newly named Allegiant Stadium, the $1.9 billion project sits just north of 50 percent complete.

Or, as Raiders owner Mark Davis said, the project is at halftime.

In the playbook of tasks needed to meet the planned July 31, 2020, completion date there are a few more milestones to be met.

Here are some of the next big occurrence­s that will be cause for celebratio­n even before the Raiders score their first touchdown in the stadium next year.

Cable net roof installati­on

In the coming months, work on installing the roof above Allegiant Stadium represents the biggest task left on the to-do list.

Crews are prepping to install the up to 850-foot long cables that will support the translucen­t polymer roof.

“They’re laying out the cable netting that will go up in the next few months,” team president Marc Badain said. “That will be the next big change.”

Don Webb, chief operating officer of Las Vegas Stadium Co., has indicated the roof, which will rest atop a crosshatch pattern of cables stretched across the opening, would be built on the floor of the stadium and lifted into

place by two cranes.

The cable net process will start in September and is slated to wrap up by the end of October, Webb said. Because of the complexity of the installati­on, Webb has referred to the process as a 17-acre Swiss watch.

“The precisenes­s of the process leaves little room for error,” Webb said.

First seat

Another milestone that is typically celebrated during a stadium’s constructi­on is the installati­on of the first seat in the 65,000-fan-capacity stadium.

The first seat could be installed any day if it fit into the project’s schedule, Webb said, but it’s all about timing.

With work on the concrete steps where the seats will be installed not slated to wrap up until the end of November and a few other tasks that could be affected by seat installati­on still to go, the first seat probably will be installed sometime in January or February, Webb said.

The seat installati­on will last several months and be completed sometime in June, according to the latest project schedule.

Lanai doors

One of the most anticipate­d features at Allegiant Stadium are the massive 80-by-215-foot lanai doors.

The doors located on the north end of the stadium open to a spectacula­r view of the Strip. With the translucen­t roof, the doors will give the look and feel of an outdoor venue but will offer the ability to control the climate when necessary.

The area where the lanai doors are located will also feature the Al Davis memorial torch. If winds 25 mph or greater are forecast for a game day, the doors will remain closed. It takes about 10 minutes to close the stadium’s lanai doors.

The process to construct the doors will be carried out as part of the exterior glazing system and is expected to be completed by the end of March.

Glass panel installati­on

The translucen­t black glass panels that will be installed around the exterior of Allegiant Stadium will give the stadium a black appearance from outside the stadium during the day, but the stadium lights will be visible come sundown.

Glass installati­on is expected to wrap up in March, when the stadium is set to be fully enclosed, Webb said.

Field tray

Crews are constructi­ng the 4-footdeep tray that will move the 9,500-ton natural grass field in-and-out of the stadium between Raiders and UNLV football games.

The Raiders will use natural turf, which will be on the field tray, while UNLV will use artificial turf, which will be located on the stadium floor.

Rolling on 13 rails through a 14-by240 foot opening on the south end of the stadium, the process for bringing the turf in or out is an intricate one.

“There’s a lot of moving parts and detail work to go on the stadium’s floor,” Webb said.

First tests on the tray are set to occur near the end of May, Webb said.

Big flush

After all of the plumbing in the stadium is complete, the team will test how the sewer system will handle a spike in use tied to a typical stadium-level event.

Dubbed the “big flush,” every toilet and urinal will be flushed at the same time as all the faucets in the stadium are turned on.

Webb expects the big flush in June. “We’re going to try and overload the system,” Webb said. “I’m serious. We’re going to play out what happens during a sold-out NFL stadium.”

Newspapers in English

Newspapers from United States