Occupancy permit for stadium set for Aug. 1

1,850 workers cover three shifts, six days a week

- By Mick Akers Las Vegas Review-journal

With two weeks to go until the targeted date for Allegiant Stadium to be substantia­lly complete, crews are on task and on budget with the $2 billion project.

The stadium is 98 percent complete and is on track to receive a temporary certificat­e of occupancy by Aug. 1, according to Jeremy Aguero, a principal for Applied Analysis who serves on the Las Vegas Stadium Authority’s staff.

“It (the stadium) will include all project elements and will meet the project standards set forth in the stadium developmen­t agreement,” Aguero said Thursday.

About 1,850 workers are covering three shifts, six days a week, to ensure the targeted July 31 completion date is met.

Current interior work includes installati­on of furniture, commission­ing food and beverage operations, installati­on of TVS in concourse areas, concession and suite areas and fine-tuning of the stadium’s mechanical systems, Aguero said.

Exterior work features installati­on of way-finding signs, parking lot strip

ing and landscape work. Crews are also busy finishing up installati­on of Raiders “legacy bricks” near the main entrance on the north end of the stadium.

Although the majority of work is complete, there was a delay in the delivery of around 4,200 club seats. Those are expected to be delivered between July 20 and Aug. 3 and are not expected to affect the approval of the certificat­e of occupancy.

Don Webb, chief operating officer of the Raiders’ constructi­on subsidiary, assured that fans would be comfortabl­e once inside the stadium, noting the temperatur­e was at 75 degrees, a stark contrast to Thursday’s expected high temperatur­e of 108 degrees outside the stadium.

Shade canopies were also installed at all the major entrances, which will give eventgoers some refuge ahead of entering the climate-controlled building.

Once the substantia­l completion date is met, there will still be a punch list of work to be completed in and around the stadium totaling $145 million, or 7 percent of the project’s $2 billion budget. The closeout date for that work is Nov. 31.

A previously noted, an unnamed “project opening event” slated for Aug. 16 is no longer included in the project’s status report. However, it still lists the sold-out Aug. 22 Garth Brooks concert and the Aug. 27 Raiders preseason game versus the Arizona Cardinals.

The report does address the uncertaint­y of the events taking place, noting the COVID-19 pandemic.

“A number of opening events continue to be scheduled for both August and September,” Aguero said.

Contact Mick Akers at makers@ reviewjour­nal.com or 702-387-2920. Follow @mickakers on Twitter.

 ?? Las Vegas Raiders ?? Crews test video boards inside Allegiant Stadium on June 23. The stadium is 98 percent complete and is on track to receive a temporary certificat­e of occupancy by Aug. 1.
Las Vegas Raiders Crews test video boards inside Allegiant Stadium on June 23. The stadium is 98 percent complete and is on track to receive a temporary certificat­e of occupancy by Aug. 1.
 ?? Erik Verduzco Las Vegas Review-journal @Erik_verduzco ?? The planned completion date for Allegiant Stadium, seen Saturday, is July 31. Work is continuing on schedule.
Erik Verduzco Las Vegas Review-journal @Erik_verduzco The planned completion date for Allegiant Stadium, seen Saturday, is July 31. Work is continuing on schedule.