Lodi News-Sentinel

High-speed rail costs off the tracks

Federal report estimates Central Valley portion of track could cost up to $10 billion

- By Ralph Vartabedia­n

LOS ANGELES — California’s bullet train could cost taxpayers 50 percent more than estimated — as much as $3.6 billion more. And that’s just for the first 118 miles through the Central Valley, which was supposed to be the easiest part of the route between Los Angeles and San Francisco.

A confidenti­al Federal Railroad Administra­tion analysis, obtained by the Los Angeles Times, projects that building bridges, viaducts, trenches and track from Merced to Shafter could cost $9.5 billion to $10 billion, compared with the original budget of $6.4 billion.

The federal document outlines far-reaching management problems: significan­t delays in environmen­tal planning, lags in processing invoices for federal grants and continuing failures to acquire needed property.

The California High-Speed Rail Authority had originally anticipate­d completing the Central Valley track by this year, but the federal risk assessment estimates that that won’t happen until 2024, placing the project seven years behind schedule.

The report, the most critical official assessment of the project to surface so far, is labeled a “confidenti­al-draft deliberati­ve document for internal use only,” and was presented by senior Federal Railroad Administra­tion executives to California rail authority board Chairman Dan Richard and Chief Executive Jeff Morales on Dec. 1 in Washington.

This analysis puts the state on notice that it could face bigger cost overruns than it ever anticipate­d and much longer delays than have been made public, a troubling critique by an agency that has been a stalwart supporter and longtime financier of the nation’s largest infrastruc­ture project.

Morales cautioned in an interview that the numbers in the analysis are only projection­s and estimates that do not account for interventi­on by the rail authority, and he asserted that the constructi­on in the Central Valley will cost less than the risk analysis indicates.

The estimates, he said, are based on a lot of assumption­s that the authority wants to ensure are correct.

“The point of doing this analysis is to identify the challenges and work through them,” he said. “They are not conclusion­s and not findings.”

The Federal Railroad Administra­tion is tracking the project because it has extended $3.5 billion in two grants to help build the Central Valley segment. The administra­tion has an obligation to ensure that the state complies with the terms, including a requiremen­t that the state has the funding to match the federal grants.

The railroad administra­tion’s analysis shows that the state authority could lose $220 million in one of the federal grants this year if it cannot submit paperwork by June 30, to meet the Sept. 30 deadline of the Obama administra­tion’s stimulus act.

To hit those milestones requires spending $3.2 million per day, a very high rate of constructi­on spending. But Morales said the rail authority’s constructi­on progress and spending rate ensure that all of the grant funds will be used. So far, the authority has spent $2.2 billion of the grant, leaving $300 million to spend.

Federal Railroad Administra­tion spokesman Matthew Lehner did not answer specific questions about the risk analysis but said that it “is a standard oversight tool used on major capital projects —

not just California.”

Lehner said that he’s confident the state can meet its deadline, “with continued focus and hard work.”

Other recent documents, however, paint a dark picture of California’s ambitious transporta­tion project and help explain some of the performanc­e problems.

Audit reports last year, for example, found that the rail authority lacks consistent management processes, takes on unnecessar­y contract risks, does not have orderly records and is short on clearly defined responsibi­lity for its top officials.

And an internal report obtained by the Times notes a just-completed survey in which employees complain that morale is low and has declined in each of the last three years. Employees interviewe­d by the Times say turnover is consistent­ly high, leaving staff overworked. The rail authority’s senior deputy, its chief administra­tive officer and its top informatio­n technology executive recently left.

Rail authority spokeswoma­n Lisa Marie Alley said the authority takes the issue seriously and that it is “currently making changes that we expect will help in that regard.”

About 80 percent of all bullet train systems incur massive overruns in their constructi­on, according to Bent Flyvbjerg, an infrastruc­ture risk expert at the University of Oxford who has studied such rail projects all over the world. One of the biggest hazards of such mega-projects is a government agency that is attempting to do something highly complex for the first time.

The California system is being built by an independen­t authority that has never built anything and depends on a large network of consultant­s and contractor­s for advice. Engineerin­g and constructi­on experts have warned that early cost and schedule problems will be difficult to reverse and that early cost increases will likely drive up the final cost of the project.

Proponents of the project, including many veteran transporta­tion experts, have said that California’s massive economy can handle higher costs for the project — even more than $100 billion — by increasing sales taxes or making firm commitment­s for additional future funding from the state’s general fund.

That theory may have to be tested soon. The federal analysis shows that the state might have to come up with another $2 billion to complete the 118 miles of constructi­on in the Central Valley, based on the new cost projection.

 ?? LUIS SINCO/LOS ANGELES TIMES ?? Invited guests sign segments of railroad track during a groundbrea­king ceremony for a bullet train station Tuesday, Jan. 6, 2015 in Fresno. The train could cost taxpayers 50 percent more than estimated.
LUIS SINCO/LOS ANGELES TIMES Invited guests sign segments of railroad track during a groundbrea­king ceremony for a bullet train station Tuesday, Jan. 6, 2015 in Fresno. The train could cost taxpayers 50 percent more than estimated.

Newspapers in English

Newspapers from United States