Rail route’s first segment sharply criticized

- By Ralph Vartabedia­n ralph.vartabedia­n@latimes.com

The state’s plan to build an initial stretch of highspeed rail line, from San Jose to a map point in the midst of Central Valley farmland, came under renewed attack at an oversight hearing Monday.

Republican­s on the House rail subcommitt­ee had sought to hold the hearing in the Silicon Valley but ran into Democratic opposition, according to sources familiar with the matter. So the group convened around folding metal tables in a nondescrip­t basement room in a San Francisco federal building.

Rep. Jeff Denham (RTurlock), chairman of the panel, chided the state for lacking a plan to complete the Los Angeles-to-San Francisco bullet train system.

“You could be stuck in a field somewhere between Shafter and Wasco … and … out of money,” Denham said.

The apparent absurdity of the abbreviate­d route was not lost on supporters.

“It seems odd,” acknowledg­ed Dan Richard, chairman of the California HighSpeed Rail Authority, “to be stopping in the middle of an almond orchard.”

He added, however, that an additional $2.9 billion from the federal government could extend the line to Bakersfiel­d, eventually capturing billions in fare revenue.

The hearing Monday largely ref lected the enthusiasm of Democrats and the skepticism of Republican­s for the $64-billion project.

“We don’t want something that has no riders, no train, no investor, only to have to wait for decades,” Denham said of the initial route.

Richard, however, told the subcommitt­ee that the project is “going smoothly.” The state’s new business plan, released earlier this year, said the project had enough sources of money from bonds, federal grants and state greenhouse gas fees to build a $21-billion line from San Jose to a point somewhere near the small agricultur­al town of Wasco, before continuing on with new money to more populated destinatio­ns.

Since then, the greenhouse gas fees, raised in socalled cap-and-trade auctions, have fallen f lat and the auctions are under a legal challenge by the state’s Chamber of Commerce. The sale of bonds has been delayed by years.

Constructi­on of the first 29 miles, from Madera to Fresno, has been funded mostly by the federal grants and without state matching funds that will have to be paid later.

But Richard said he had “great confidence” that the cap-and-trade auctions would survive and that ultimately private investors would help the state complete constructi­on, closing what is now a $43.5-billion funding shortfall that would be needed mainly to cross the Tehachapi and San Gabriel mountains.

But even some Democrats are beginning to worry that the project could turn into a train ride to nowhere, with snippets of the route scattered across the state as Bay Area and Los Angeles deal makers siphon funds.

What if the state ultimately fails to connect the Bay Area to Southern California, asked Rep. Zoe Lofgren (D-San Jose).

“I don’t want my name [or] the governor’s name to be associated with a piece of track that isn’t connected to the rest of the state,” she said.

But Richard continued with an answer that provided insight into how the state might justify an isolated segment if the entire system never gets built.

The Central Valley segment, he said, would eliminate 55 grade crossings and provide a dedicated line for Amtrak trains, relieving overburden­ed freight track.

“There is a lot that we are doing that will have immediate benefit,” he said.

 ?? Luis Sinco Los Angeles Times ?? A PEDESTRIAN crosses railroad tracks in Fresno where a new bullet train station will be built.
Luis Sinco Los Angeles Times A PEDESTRIAN crosses railroad tracks in Fresno where a new bullet train station will be built.