Los Angeles Times

Time bombs in the water system

- MICHAEL HILTZIK

For the Metropolit­an Water District, which serves 19 million residents of Southern California, the wake-up call sounded in December 1999.

That’s when a water main on the outskirts of Irvine suffered a catastroph­ic blowout, spilling 5 million gallons and shutting off service to some 700,000 residents of south Orange County, some for more than a week. Although the blowout was later ascribed to “operator error,” it exposed some fundamenta­l weaknesses in the MWD system and prompted the district to undertake a closer inspection.

The district found hundreds of leaks and breaks, which it blamed on premature deteriorat­ion in the prestresse­d concrete cylinder pipeline. That was just the beginning. So-called PCCP throughout the MWD system — at least 100 miles

of the 160 miles of pipe made from the material — has been judged suspect and possibly in need of repair or replacemen­t.

The first phase of that program was launched by the MWD board on Aug. 15 with the approval of a nearly $40-million project to install steel pipe to reline 4.5 miles of PCCP under the streets of Long Beach and Lakewood. The work is scheduled to begin in September and take seven months to complete. A second phase of relining on the same trunk line will be presented to the board for approval next summer.

The MWD expects to spend as much as $2.5 billion on the task over the next 20 to 25 years, but that only opens a window on the magnitude of the infrastruc­ture reconstruc­tion facing water systems all over the country. Repairing or replacing PCCP mains nationwide could cost $40 billion, according to a technical assessment produced in 2008 for the U.S. Environmen­tal Protection Agency and the American Water Works Assn. Modernizin­g the nation’s aging water infrastruc­ture, including ancient iron pipelines common in downtown parts of older Eastern cities, could cost many billions more.

In California, that task includes building the controvers­ial delta tunnels to convey water from Northern to Southern California. The tunnels and associated works are estimated to cost more than $16 billion, of which the MWD would pay 26%, adding $2 to $3 a month to the average residentia­l water bill. The project is still uncertain, with litigation and doubts from water users and agencies around the state among the obstacles.

We’ve written recently about the impact that infrastruc­ture spending could have on water affordabil­ity in coming decades. But one often-overlooked aspect of the issue is how decisions taken in the past can reverberat­e down through the decades.

The problems caused by PCCP are a good example. The pipes, made from steel tubing wrapped in concrete and steel reinforcin­g wire, often were used for highcapaci­ty, high-pressure water lines. As a result, their failures could be catastroph­ic and costly. Reports of pipe failures “can be sensationa­l, particular­ly where the resulting flood damage provides spectacula­r footage for the 10 o’clock news,” observed the 2008 study.

Experts also noted that even limited deteriorat­ion could lead to major trouble. “It takes only one bad pipe section to generate a significan­t pipeline failure,” a 2012 engineerin­g study warned. That’s what happened in the 1999 blowout, according to the MWD: Had the line not been already weakened by corrosion, it might have survived the operator error that resulted in the blowout.

PCCP lines have been a cause of increasing nervousnes­s among water system managers since the 1990s. That’s when the consequenc­es of changes in standards for the lines in the 1970s became apparent.

When the MWD started installing PCCP lines in the 1970s, according to Gordon Johnson, the district’s chief engineer, they were considered virtually interchang­eable with steel pipelines. “We bid them against each other, and took the one that was the lowest bid,” Johnson told me.

Both were expected to last 70 to 100 years. But while the steel pipelines are still mostly “as good as new,” Johnson says, “PCCP just doesn’t have the same life.”

The problem appears to be the liberaliza­tion of manufactur­ing standards in the early 1970s, just as the MWD started using the material. Perhaps complacent­ly, engineerin­g organizati­ons promulgate­d liberalize­d standards for PCCP, incorporat­ing reinforcin­g steel wires that were stronger, but also thinner. Those wires turned out to be more vulnerable to corrosion and brittlenes­s than expected.

“They thought they’d come up with a new technique that would be cheaper,” says Jeffrey Kightlinge­r, general manager of the MWD. The reality is that the lifespan of PCCP from that era is about half that of steel pipe.

“When the standards changed, you came into pipe that was more stressed than before,” says Graham E. C. Bell, a coauthor of the 2008 study. The majority of catastroph­ic PCCP failures have been traced to pipes of the 1972-1978 vintage, when the eased standards were in effect. By the early 1980s, manufactur­ing standards had been tightened up considerab­ly.

Some engineers say PCCP is still a good pipeline material in many circumstan­ces. “Some owners swear by it because it performs very well,” says Michael Higgins, an executive at Pure Technologi­es, which assists utilities in assessing the condition of their mains, and a coauthor of the 2012 paper. The overall failure rate is less than 4%, he says. But PCCP pipes tend to fail suddenly and catastroph­ically, creating dangerous conditions and outsized disruption.

According to Bell’s study, overpressu­re leads to cracks in the concrete coating, which allows water to enter the pipe from the surroundin­g soil and corrode the reinforcin­g wires, which break and in turn allow water to corrode other components of the pipe. Steel pipes tend to spring leaks, which can be patched; “the failure mode of PCCP is usually sudden,” the study said.

The PCCP problem is most acute in the East, in part because the region was served by a now-defunct New Jersey company that allegedly manufactur­ed some of the most troublesom­e lines. In 1997, Pinellas County, Fla., won a $10million judgment over a 13-mile PCCP line that was installed in 1978, failed in 1979 and exploded again during a 1980 pressure test and twice more by 1994 — all at pressures well below what the line had been built to bear.

The Maryland suburbs of Washington have been particular­ly beleaguere­d by 350 miles of concrete mains “prone to exploding without warning,” the Washington Post reported in 2013.

The MWD, to be sure, says it already had become wary of concrete pipelines when the Irvine blowout occurred — the district had stopped using the pipe in the mid-1990s, after the first string of failures emerged, including several ruptures in San Diego County mains in the 1980s and 1990s. But the already-installed pipes remain undergroun­d, like time bombs.

 ??  ??
 ?? Al Schaben Los Angeles Times ?? METROPOLIT­AN Water District workers fit a section of new custom-made steel pipe to replace the original concrete pipeline in Irvine after it ruptured in December 1999. The blowout spilled 5 million gallons of water.
Al Schaben Los Angeles Times METROPOLIT­AN Water District workers fit a section of new custom-made steel pipe to replace the original concrete pipeline in Irvine after it ruptured in December 1999. The blowout spilled 5 million gallons of water.

Newspapers in English

Newspapers from United States