Los Angeles Times

RAIL PROJECT HITS BRAKES AGAIN

To trim costs, an additional 30 miles of the bullet train route will see lower speeds, documents show.

- By Ralph Vartabedia­n

The California bullet train will have another slow segment of track as part of a new cost-savings measure, state rail authority documents reveal.

Technical documents attached to the authority’s 2018 business plan show that it no longer aims to have dedicated tracks designed for speeds of up to 220 mph over a 30-mile stretch south of San Francisco.

Instead, the system would operate between San Jose and Gilroy at 110 mph on ground-level tracks on or adjacent to an existing rightof-way owned by Union Pacific. The route would make 32 highway crossings, requiring sophistica­ted barrier gates and sharing a corridor that carries freight and commuter rail.

The decision is the third compromise the rail authority has made for money or politics that would create slower sections of track, each incrementa­lly adding travel time to an alternativ­e form of transporta­tion promised to link Los Angeles and San Francisco in less than three hours.

In this case, adding several minutes to the trip is estimated to save about $1.7 billion, a significan­t sum for a project critically short of funding. The 2018 business plan, released last week, acknowledg­ed there is not enough money to build a partial operating system from San Francisco to Bakersfiel­d by 2029.

The original design for the San Jose-to-Gilroy segment had lengths of costly elevated track and would have taken significan­t private land. A rail authority spokespers­on said the new plan also will minimize community disruption and environmen­tal impacts.

Whether the new plan succeeds hinges on whether Union Pacific agrees to allow use of its right-of-way, according to the documents. It is unclear whether the railroad company will go along — and if so, at what cost.

“There is no formal agreement in place regarding the 2018 business plan or its contents,” said Union Pacific spokesman Justin Jacobs, though the parties regularly discuss the state’s “evolving plans.”

In a 2010 letter, Union Pacific warned the rail authority it would not agree to allow the high-speed rail system to use any part of its right-ofway or to be so close to its tracks that it would impair safety or its freight movements.

Frank Vacca, the authority’s chief of rail operations, said the state is making progress from Union Pacific’s original position and hopes he can have an agreement by the end of this year.

For six years, the rail authority has been cutting deals that would nudge up travel times.

In 2012, the authority agreed with political leaders in the Bay Area to eliminate a controvers­ial elevated viaduct through wealthy Peninsula communitie­s. Instead, over a 50-mile stretch from San Jose to San Francisco, the system would share existing tracks owned by Caltrain, a commuter service operated by a local joint powers authority.

Several years ago, the rail authority said it would share about 11 miles of right-ofway, if not tracks, with the Metrolink system between Burbank and downtown Los Angeles.

In total, about 91 miles of rail above ground involve shared track or right-of-way that will restrict speeds to about 110 mph. Even that speed is questionab­le.

Grady Cothen, an attorney and former chief of safety regulation­s at the Federal Railroad Administra­tion, said in an interview with The Times last year that 110-mph speeds are unrealisti­c in dense urban areas.

In statements to the public, rail officials have also suggested they would not run trains at full speed through urban residentia­l neighborho­ods.

Tunnels are another area of restricted speed. In 2016, the rail authority said in a technical document that it would save money by reducing the diameter of tunnels, which would necessitat­e slowing trains to about 200 mph. In one curved section of a Southern California tunnel, train speeds would be as low as 130 mph, according to a 2014 technical document. In total, 45 miles of tunnels are planned for the system, according to the business plan.

Of the roughly 434 miles of track between Los Angeles and San Francisco, 136 miles — nearly one-third of the total — could have at least some speed restrictio­ns.

Exactly how much time the San Jose-to-Gilroy slow section would add to a trip is not disclosed in the documents. At 110 mph over 30 miles, the passage would take an additional eight minutes compared with 220 mph. But Vaca, the rail official, said the speed reduction amounts to only three to four minutes, because the original design for the route had some curved sections that also reduced the speed.

The authority is legally required under the 2008 Propositio­n 1A bond act to design its system to get a train from Los Angeles to San Francisco in 2 hours and 40 minutes, though it is not required to operate trains on that timetable. Vaca said the system will beat that design requiremen­t with some time to spare, though he did not disclose the exact travel time that the rail authority’s model now predicts.

Outside rail experts say it is improbable that the rail would ever meet the 2-hour, 40-minute trip time in actual operations. In the business plan’s supporting documents, the rail authority lists a timetable “example” that shows the fastest fulllength trip would be 3 hours and 30 minutes. Trains with more stops would take 4 hours and 5 minutes. Nonetheles­s, Vaca said he is confident that a one- or two-stop train will make the trip in under three hours.

Issues of cost, speed, ridership and fares are intertwine­d in a project facing mounting political and financial challenges. Internally, the rail authority is undergoing a management shake-up with the arrival of new Chief Executive Officer Brian Kelly and several other key executives, who are trying to restore credibilit­y as the price tag rises and constructi­on falls further behind schedule.

In one of his early acts, Kelly ordered an immediate review of the authority’s new cost estimates, which price the project at $78.3 billion, with the potential to fall as low $63.2 billion or rise as high as $98.1 billion. In the business plan itself, Kelly ordered “a further assessment of the reasonable­ness of the cost estimates and the ranges.”

Such cost estimates are supposed to take into considerat­ion every yard of concrete and every pound of steel needed for constructi­on, as well as many other factors — a laborious task that can take one or two years for a team of estimators.

An authority spokespers­on said the estimates were developed before Kelly took over the project Feb. 1, and the new review is aimed at making sure the range includes factors that could raise or lower costs.

Among those factors could be the electrical power grid in the Central Valley, which the business plan revealed may not have enough juice in some areas to operate the electric trains.

As a result, the rail authority is in discussion­s with PG&E, the electric utility that serves the area, to build new transmissi­on lines, the plan said. The authority’s spokespers­on said those discussion­s have been going on for five years and involve who will pay for it.

 ?? California High Speed Rail ?? A PERGOLA, part of the bullet train’s San Joaquin River Viaduct project, will allow the high-speed train to pass over freight tracks.
California High Speed Rail A PERGOLA, part of the bullet train’s San Joaquin River Viaduct project, will allow the high-speed train to pass over freight tracks.

Newspapers in English

Newspapers from United States