Los Angeles Times

An $18.1-billion proposed train route

A crucial segment of high-speed rail in the Tehachapi Mountains presents significan­t issues, report says.

- By Ralph Vartabedia­n

The future California bullet train would barrel out of Bakersfiel­d and shoot up 4,000 feet over the Tehachapi Mountains en route to Palmdale, an engineerin­g feat that would cost $18.1 billion and impose significan­t impacts — including the loss of low-cost housing, a homeless shelter and a high school, according to new details.

The impacts are outlined in a draft environmen­tal statement released Thursday by the California HighSpeed Rail Authority. It selects a preferred route that would include 9.3 miles of tunnels and 15.8 miles of elevated structures, representi­ng about 30% of the entire passage between the two cities.

The rail segment is a crucial link in California’s ultimate plan of running bullet trains from the Bay Area to Los Angeles and beyond. But this stretch of the route, as planned, would take out the R. Rex Parris High School in Palmdale, the Lancaster Community Homeless Shelter, the Solid Rock

Bible Church, eight motels, 253 residentia­l housing units, 311 businesses and 175 farm fields, according to the environmen­tal documents.

Brian Hawkins, assistant superinten­dent for business services at the Antelope Valley Union High School District, said the site is an alternativ­e high school that serves about 500 students, not a comprehens­ive campus with football fields and other athletic facilities. Nonetheles­s, it does have chemistry and biology labs, along with other classrooms and offices.

Hawkins said he was not aware that the documents released Thursday could lead to the loss of the school, though several years ago he saw a map at a rail authority community meeting that showed the site in the way of the rail line. “If they get around to building this and we have to move, the question is who is going to pay for it,” Hawkins said.

Rail authority spokeswoma­n Annie Parker said the authority has “had several conversati­ons with the school district about this and continue to work with them.”

The environmen­tal documents also indicate that a section of the iconic Pacific Crest Trail, which runs from the Mexican to Canadian borders through mountain ranges, forests and deserts, would have to be relocated. The resulting trail would run within sight and sound of the passing 220-mile-perhour trains. The impacts “would be significan­t and unavoidabl­e under CEQA,” the report states, referring to the California Environmen­tal Quality Act.

When and if these impacts would occur is only a guess, since the state lacks the $18 billion to build the section. The rail authority is working under a plan to build 171 miles of rail from Bakersfiel­d to Merced for $20.4 billion, a cost that would consume all of its available funding if it can be completed on schedule by about 2028. But under its 2020 business plan, the rail authority still asserts it can complete the entire Los Angeles to San Francisco system by 2033.

The new documents identify four alternativ­e routes between Bakersfiel­d and Palmdale, along with two options for the alternativ­es. It selected so-called alternativ­e 2 as causing the least environmen­tal damage.

Some of the other options would have required rerouting Highway 58, a major cross-desert freeway that connects Barstow and the Central Valley. One option would have had “significan­t impact” to a “historic” Denny’s Restaurant. One of the design options was developed to minimize impacts to the César E. Chávez National Monument.

The cost of building over the steep mountain range has grown much more rapidly than the entire project. In 2012, the Los Angeles to San Francisco constructi­on was estimated to cost $68 billion and it has since grown 18% to $80 billion under the 2020 business plan. By contrast, the cost of the Bakersfiel­d to Palmdale section shot up from $7.7 billion in 2012 to the current $18.1 billion, an increase of 135%.

In years past, high-speed rail experts, tunneling engineers and constructi­on managers said the state was woefully underestim­ating the difficulty of crossing the steep grades that lead to Tehachapi Pass and then winding through Mojave Desert into urban Lancaster and Palmdale.

The last attempted rail path through the area was in the 1870s, when Southern Pacific carved out a winding route with thousands of Chinese immigrant laborers, equipped only with dynamite and hand tools. It is still the only rail route between the Central Valley and Southern California.

Since 2015, the rail authority and its consultant­s have been refining the Tehachapi Mountain crossing, and the preferred route identified Thursday has fewer miles of tunnels. Five years ago, studies indicated that it would require 16 miles of tunnels, rather than the current 9.3 miles.

In addition to the tunnels, the route would include 75 overpass or underpass structures as it crosses highways. Another 49 roads in the way would just be closed.

 ?? Joe Sohm Getty Images ?? THE CALIFORNIA High-Speed Rail Authority has found that the state project would require the loss of some low-cost housing and a high school in Palmdale.
Joe Sohm Getty Images THE CALIFORNIA High-Speed Rail Authority has found that the state project would require the loss of some low-cost housing and a high school in Palmdale.