Caltrans crews are scheduled to work on a number of projects in the region.

Here’s what drivers can expect this coming week:

Yuba County long-term projects

State Route 20: Work continues a $16.8 million project funded in part by Senate Bill 1, the Road Repair and Accountabi­lity Act of 2017, to rehabilita­te the pavement, widen shoulders and realign the roadway between Loma Rica Road and Spring Valley Road.

Project informatio­n and constructi­on updates are available at www. Fixyuba20.com No traffic-interferin­g work is scheduled.

State Route 20: Work continues on a $61.5 million project funded in part by Senate Bill

1, the Road Repair and Accountabi­lity Act of

2017, to straighten and flatten roadway curves and slopes, widen shoulders, construct a new bridge and rehabilita­te a 4.5-mile section of roadway in the Browns Valley area. Constructi­on is expected to be completed in 2021. Project informatio­n and constructi­on updates are available at www. Fixyuba20.com.

State Route 20 between Marysville Road and Timbuctoo Road: Motorists may expect intermitte­nt one-way traffic control from 6:30 a.m. to 4 p.m. Monday through Wednesday, 6:30 a.m. to 3 p.m. Thursday, 6:30 a.m. to 2 p.m. Friday and 6:30 a.m. to 4 p.m. Saturday for miscellane­ous highway constructi­on work.

State Route 20: Work continues a $54 million project by Caltrans to straighten curves, widen shoulders, construct a new bridge and rehabilita­te a 2-mile section of roadway in the Timbuctoo area. Constructi­on is expected to start this spring.

Project informatio­n and constructi­on updates are available at www. Fixyuba20.com.

State Route 20 between the Parks Bar Bridge over the Yuba River and Lower Smartsvill­e Road: Motorists may expect intermitte­nt one-way traffic control from 7 a.m. to 3 p.m. Monday through Friday and 6 a.m. to 3 p.m. Saturday for miscellane­ous roadwork.

State Route 70: Work continues an $83 million funded in part by Senate Bill 1, the Road Repair and Accountabi­lity Act of 2017, to replace the Simmerly Slough Bridge. Completion is expected in spring 2022. Project informatio­n and constructi­on updates are available at www. Fixhighway­70.com No traffic-interferin­g work is scheduled.

Short-term projects

State Route 49 between Marysville Road and Yuba Pass Summit: Motorists may expect intermitte­nt one-way traffic control at various locations from 6:45 a.m. to 3:45 p.m. Monday through Thursday for miscellane­ous maintenanc­e work.

State Route 65 at Hooper Street: Motorists may expect the right shoulder on Hooper Street closed through Monday for local paving, curb, gutter and sidewalk work.

State Route 70 from the State Route 65 junction to about a mile north of Feather River Boulevard: Southbound motorists may expect various lane restrictio­ns from 6 p.m. to 7 a.m. Sunday through Thursday for pavement grinding and paving work.

State Route 70 at Mcgowan Parkway: Southbound motorists may expect temporary ramp closures sometime between 6 p.m. and 7 a.m. Sunday through Thursday for pavement grinding and paving work. The Plumas Lake Boulevard ramps will remain open when the Mcgowan ramps are closed.

State Route 70 at

Plumas Lake Boulevard: Southbound motorists may expect temporary ramp closures sometime between 6 p.m. and 7 a.m. Monday through Thursday for pavement grinding and paving work. The Mcgowan Parkway ramps will be open when the Plumas Lake ramps are closed.

State Route 70 at Erle Road: Northbound motorists may expect the right shoulder of the offramp closed from 7 a.m. to 9:30 p.m. Monday through Saturday for PG&E to perform gas line work on Lindhurst Avenue.

State Route 70 between 6th Street and First Street: North- and southbound motorists may expect various lane restrictio­ns from 9 p.m. to 5 a.m. Sunday and Monday for utility work.

State Route 70 between 14th Street and Cemetery Road: Northbound motorists may expect intermitte­nt lane and shoulder restrictio­ns from 9 p.m. to 5 a.m. Sunday and Monday for core drilling work.

State Route 70 between Magnolia Road and Boyer Road: Motorists may expect one-way traffic control from 9 a.m. to 4 p.m. Monday for tree work.

Sutter County long-term projects

State Route 20: Work continues on a $37.7 million project funded in part by Senate Bill 1 (SB

1), the Road Repair and Accountabi­lity Act of 2017, to restore nearly 12 lane miles of pavement between Lytle Road and the

Sutter Bypass, widen the shoulders and replace the Wadsworth Canal Bridge. Completion is expected in 2020.

State Route 99 between the east end of the Sutter Bypass and Lytle Road: Motorists may expect oneway traffic control through 8 a.m. to 7 p.m. Monday through Thursday, 8 a.m. to 4 p.m. Friday and 8 a.m. to 7 a.m. Saturday for striping work.

State Route 99: Constructi­on continues on a $36 million pavement and streetscap­e project by Caltrans and the

City of Live Oak and funded in part by Senate Bill 1, the Road Repair and Accountabi­lity Act of 2017, and a federal TIGER grant to replace the old pavement, flatten the roadway, construct new sidewalks, curbs and gutters, upgrade drainage systems, and improve traffic signals, bicycle and pedestrian signals between Pennington

Road and Elm Street. Completion is expected in 2021. Project informatio­n and constructi­on updates are available at www. Liveoak99.com.

State Route 99 between Ivy Street and Nevada Street north: North- and southbound motorists may expect various lane, auxiliary lane and shoulder restrictio­ns from 6 a.m. to 6 p.m. Monday through Saturday for undergroun­d waterline work.

State Route 99 at Birch Street, Ash Street, Walker Way and Archer Avenue: Motorists may expect Birch, Ash, Walker and Archer closed at State Route 99 around-the-clock through late October for roadway constructi­on. Motorists should use Elm Street or seek alternativ­e routes.

Special event

State Route 65 at Hooper Street: North- and southbound motorists may expect the right shoulder closed through November 5 for a portable message board publicizin­g traffic control measures for an annual fall pumpkin farm event in Wheatland.

Short-term projects

State Route 99 between Hunn Road and Bridge Street: North- and southbound motorists may expect the right shoulder closed through October 30 for Yuba City’s curb, gutter and sidewalk improvemen­ts on Franklin Boulevard.

State Route 99 at Barry Road: Northbound motorists may expect various lane restrictio­ns from 7 a.m. to 5 p.m. Tuesday for guardrail work.

State Route 99 from

0.33 north of Sacramento Avenue to 0.5 south of Wilson Road: Southbound motorists may expect various lane restrictio­ns from 6 p.m. Wednesday to 7 a.m. Thursday for striping work.

State Route 99 from 1,980 feet north of O’banion Road to 560 feet north of Smith Road: North- and southbound motorists may expect various lane restrictio­ns from 6 p.m. to 7 a.m. Wednesday and Thursday for striping work.

State Route 99 from 1,980 feet north of O’banion Road to Bogue Road: Northbound motorists may expect various lane restrictio­ns from 6 p.m. Thursday to 7 a.m. Friday for striping paving work.

State Route 99 from Bogue Road to 560 feet north of Smith Road: Northbound motorists may expect various lane restrictio­ns from 7 p.m. to 7 a.m. Wednesday and Thursday for striping work.

State Route 113 between Cranmore Road and Knights Road: Motorists may expect one-way traffic control from 8 a.m. to 3:30 p.m. Thursday for tree work.y

State Route 113 between Pelger Road and Reclamatio­n Road: Motorists may expect oneway traffic control from 8 .m. to 3:30 p.m. Monday through Wednesday for tree work.

Colusa County long-term projects

Interstate 5: Work continues on a $5.7 million project to upgrade the water and wastewater systems at the north- and southbound Maxwell Safety Roadside Rest

Areas. The rest areas are scheduled to be closed until the improvemen­ts are completed in early winter. The Willows rest areas in Glenn County or the Dunnigan rest areas in Yolo County remain open.

State Routes 20/45:

Work continues on a

$19.3 million project by Caltrans, the City of Colusa and Colusa County project million and funded in part by Senate Bill 1, the Road Repair and Accountabi­lity Act of 2017, to replace the old pavement, flatten the roadway, construct new sidewalks, curbs and gutters and improve drainage between Market Street and Butte Vista Way. Completion is expected in 2020.

State Routes 20/45 between 2nd Street and Cynthia Drive: East- and westbound motorists may expect various lane, shoulder and median restrictio­ns from 6 a.m. to 6 p.m. Monday through Thursday and 6 a.m. to 3 p.m. Friday for pavement work.

Short-term project

State Route 16 between Bear Creek in Colusa and Rumsey Canyon in Yolo: Motorists may expect one-way traffic control at various locations from 6 a.m. to 6 p.m. Monday through Friday for wildfire-related emergency tree and debris removal, culvert clean-up, drainage and erosion control work.