Milwaukee Journal Sentinel

DIRE STRAITS

County’s maintenanc­e backlog for parks now ‘seemingly insurmount­able,’ report says

- Don Behm

Milwaukee County officials are not making progress on reducing the evergrowin­g to-do list of costly building and road repair or replacemen­t projects they face at public parks, recreation­al sites and other cultural assets, a new report says.

The county now faces “a seemingly insurmount­able backlog” of tens of millions of dollars worth of deferred maintenanc­e, and lacks the resources to make headway in paring it down, the Wisconsin Policy Forum warns in the report.

If this was football, the county would be penalized for “Delay of Game” and that is the title of the nonpartisa­n forum’s report released Friday.

In the real world, however, “the penalty for delaying solutions could be far more severe,” Wisconsin Policy Forum president Rob Henken said.

The threat of a growing backlog is that some assets would continue to deteriorat­e to the extent that use of the properties down the road could be limited, he said.

“This report illustrate­s several of the challenges we have in Milwaukee County with regards to our infrastruc­ture,” Milwaukee County Executive Chris Abele

said. “Our county parks alone have built up more than $200 million in deferred maintenanc­e.”

To help deal with the backlog and other budget problems, Abele and County Board officials intend to ask the state to increase shared revenue payments to counties and to authorize counties to establish new revenue sources.

“We’re working to build a coalition throughout our community and across Wisconsin to create a state funding solution and address our biggest funding challenges,” Abele said.

Forum researcher­s reviewed asset condition reports prepared by county department­s and cultural institutio­ns, such as the Mitchell Park Domes.

Among the report’s findings:

❚ The Domes are in poor condition with up to $30 million in deferred repairs.

❚ Fully 16.5 miles of county parkways — more than 26 percent of the total 63 miles of parkways — need immediate reconstruc­tion while an additional 29 miles need reconstruc­tion within the next decade.

❚ About 39 percent of county parking lots should be reconstruc­ted immediatel­y while an additional 46 percent need reconstruc­tion in the next two to 10 years.

❚ About 12 percent of the 108 miles of park walkways are in need of immediate reconstruc­tion while an additional 65 percent will require reconstruc­tion in the

“This report illustrate­s several of the challenges we have in Milwaukee County with regards to our infrastruc­ture. Our county parks alone have built up more than $200 million in deferred maintenanc­e.” Chris Abele, Milwaukee County executive

next two to 10 years.

❚ About 48 percent of the county’s 95 tennis courts and 54 percent of its 82 basketball courts need reconstruc­tion within the next decade.

Daunting funding needs

To meet the requests from cultural institutio­ns and parks for major repair and constructi­on projects in 2019 alone, the county would need to more than double capital spending on cultural institutio­ns, from $6.2 million to $13.9 million, and increase spending nearly tenfold on parks, from $2.4 million to $23 million, according to the report.

“Meeting all parks, recreation and cultural capital requests for the next four years would require a 135 percent increase in spending, from $82.6 million to $194.1 million, over budgeted spending of the past four years,” the report said.

Neither of those targets could be met under a long-standing and selfimpose­d county policy to limit borrowing each year with a goal of restrainin­g the county’s total debt load.

The county issues bonds to generate revenue that pays for 80 percent of all major constructi­on projects, Budget Director Joe Lamers said in discussing the policy.

To limit growth of debt from bonding, the policy requires that the remaining 20 percent of those capital projects be financed with cash and that money comes out of the annual property tax levy.

For 2019, the amount of cash-financed constructi­on projects is estimated to be $10.9 million. So that much of the levy is not available to help pay costs to operate county programs.

Total bonding each year also is kept in check by limiting annual increases to 3 percent under the policy, Lamers said.

For 2019, the county could not issue more than $43.6 million in bonds for capital projects to comply with the policy.

Policymake­rs could remove the cap and increase total debt by an even larger amount each year.

But debt is repaid with a portion of the county’s property tax levy each year.

The more debt there is to repay, the greater the amount of tax levy needed for that purpose, prompting larger tax increases, Lamers said.

“It’s a real dilemma for the county,” Henken said. “To the extent you increase debt to take on a greater share of the backlog, you increase the tax levy” needed to repay the debt.

“For the county, the question is what can taxpayers afford?” he said.

 ?? MIKE DE SISTI / MILWAUKEE JOURNAL SENTINEL ?? Ken Glyzewski, a foreman with Masonry Restoratio­n of Milwaukee, works in the Tropical Dome at the Mitchell Park Horticultu­ral Conservato­ry in 2016 to place steel cable and brackets on the internal frame that will support wire mesh. The mesh protects the public by preventing concrete that flakes off the aging frame from falling onto walkways.
MIKE DE SISTI / MILWAUKEE JOURNAL SENTINEL Ken Glyzewski, a foreman with Masonry Restoratio­n of Milwaukee, works in the Tropical Dome at the Mitchell Park Horticultu­ral Conservato­ry in 2016 to place steel cable and brackets on the internal frame that will support wire mesh. The mesh protects the public by preventing concrete that flakes off the aging frame from falling onto walkways.
 ?? RICK WOOD / MILWAUKEE JOURNAL SENTINEL ?? Wisconsin Sports Group spent $30,000 in 2016 to transform four underused and deteriorat­ed tennis courts at Lincoln Park into a futsal stadium with two courts. This is an example of how private groups can help the county reduce its deferred maintenanc­e backlog and create new recreation­al opportunit­ies at no cost to the public.
RICK WOOD / MILWAUKEE JOURNAL SENTINEL Wisconsin Sports Group spent $30,000 in 2016 to transform four underused and deteriorat­ed tennis courts at Lincoln Park into a futsal stadium with two courts. This is an example of how private groups can help the county reduce its deferred maintenanc­e backlog and create new recreation­al opportunit­ies at no cost to the public.
 ?? MIKE DE SISTI AND CHELSEY LEWIS / MILWAUKEE JOURNAL SENTINEL ?? The Mitchell Park Domes are in poor condition with up to $30 million in deferred maintenanc­e.
MIKE DE SISTI AND CHELSEY LEWIS / MILWAUKEE JOURNAL SENTINEL The Mitchell Park Domes are in poor condition with up to $30 million in deferred maintenanc­e.

Newspapers in English

Newspapers from United States