Some constructi­on audits late, reviewed by Diamantis himself

- By Andrew Brown and Dave Altimari

It took the state 12 years — the same amount of time a student can pass from first grade to college — to conclude that the town of Manchester owed it nearly $5 million due to “ineligible costs” in a state-financed reconstruc­tion of its middle school, Bennet Academy.

The good news for Manchester is that the auditors worked for the Office of School Constructi­on Grants & Review, the same office that initially signed off on the spending. After an appeal to the office’s director, Kostantino­s “Kosta” Diamantis, he agreed to waive the debt.

“Luckily, Kosta agreed with our argument,” said Kimberly Lord, the town’s finance director, who said the state’s initial finding didn’t take into account special legislatio­n that altered the reimbursem­ent rate.

The Manchester case, one of 80 reviewed by the Connecticu­t Mirror, exposes some of the issues now being reviewed by forensic audits commission­ed by the administra­tion of Gov. Ned Lamont: audits were woefully late, and the decision to waive some of the overpaymen­ts to towns essentiall­y rested with one man — Diamantis.

The audits, obtained by CT Mirror through a Freedom of Informatio­n request, were completed between 2018-2020 and will be part of the forensic audit initiated by the state after the federal government launched an investigat­ion of school constructi­on grants overseen by Diamantis.

The federal investigat­ion began last October, shortly before Diamantis was fired from his position as deputy secretary of the Office of Policy and Management and simultaneo­usly retired from his job as head of OSCG&R. The Lamont administra­tion then moved the school constructi­on grant program, which was transferre­d to OPM when Diamantis was appointed deputy secretary, back to the Department of Administra­tive Services.

DAS Commission­er Michelle Gilman and Deputy Commission­er Noel Petra announced last month that the agency is hiring an outside firm to “audit the auditors” who were on Diamantis’ school grants team.

Hunting for old records

The CT Mirror’s review of the audits reveals a dysfunctio­nal system for examining and managing billions of dollars in school constructi­on projects.

The records show OSCG&R was years behind in auditing school projects, mainly because municipali­ties weren’t submitting the proper form, called an “ED049F,” to close out their constructi­on projects and auditors weren’t properly tracking the projects.

The review also found 15 projects, including the Bennet Academy job, in which auditors determined the municipali­ty owed the state money. While a few paid the bill, some municipali­ties got the costs waived and at least one town inquired how to pay back the state but never got a response from OSCG&R, the audits show.

Many of those audits were conducted at least a decade after projects were completed, requiring local officials to hunt for old records to prove they spent the state’s money correctly.

“We had to go back and try to retrace everything and we discovered there had been special legislatio­n passed that altered what the reimbursem­ent rate should have been,” said Lord.

The Manchester middle school cost about $14 million to build, but auditors determined the state should only cover about $9 million and that the rest were “ineligible costs.” Lord said the special legislatio­n should have negated the auditors’ findings.

Nine months after getting the bill, Manchester officials presented their case to Diamantis.

In a January 2020 e-mail to Manchester officials, Michelle Dixon, an education consultant on Diamantis’ 15-member school constructi­on grant team, wrote that the state would “grant an ineligible costs waiver that effectivel­y reduces ineligible constructi­on costs typically due projects of this type with Director (Diamantis’) approval.”

In an interview Tuesday, Diamantis said that, as director, he had the ability to issue an “ineligible cost waiver” during the audit process.

“I get recommenda­tions from my team and if they agree we should waive a cost then I can do that,” Diamantis said.

While most of the audits were directed to the DAS commission­er, Diamantis and other members of his team, three audits were sent directly to Diamantis and not to the commission­er. One of those three was for the Birch Grove Primary School project in Tolland, which is part of the federal investigat­ion into how OSCG&R and Diamantis, in particular, may have influenced school building contracts.

The federal grand jury has subpoenaed not only Tolland officials for documents related to their communicat­ion with Diamantis about that project, but also the general contractor, D’Amato Constructi­on of Bristol, and the constructi­on manager, Constructi­on Advocacy Profession­als (CAP) — both of which were hired through no-bid contracts.

Diamantis said the Birch Grove audit may have come directly to him because it was only for the portion of the project that was 100% funded by the state. There were other parts of the project that the state funded 89%, he said.

“That would have just been a desk audit because the project was fully funded so there really was nothing to audit or review,” Diamantis said.

In a written response last week to questions from the CT Mirror, DAS spokeswoma­n Lora Rae Anderson confirmed that when OSCG&R was moved to OPM, the audit unit reported directly to Diamantis. She said that “structure was changed when OSCG&R moved back to DAS in late October 2021.”

“The school constructi­on audit division has a separate reporting chain through the DAS Business Office and not to the Director of OSCG&R,” Anderson said. “This change was meant to separate out the audit function from grants and plan review program.”

At a press conference in early March to discuss the agency’s legislativ­e priorities, Petra said changing the auditing process was a clear priority when they began reviewing the program last October.

“One of the first things we did when OSCG&R came back to DAS was to remove the internal auditors from that team and put them at an arm’s length distance over in the business office,” Petra said. “And then we followed up with a meeting where I made it very clear to them that they no longer had any reporting to me or the director of OSCG&R at all.”

Petra added that he told audit team that “… if any problems come up, if there was any question that made them concerned or raised any concerns at all, they were to go directly to the commission­er.”

But Diamantis disputed that the auditors reported to him directly and said he welcomed the state’s forensic audits.

Mostly formulaic

The state received a federal grand jury subpoena seeking all emails, text messages and attachment­s involving Diamantis and a broad range of constructi­on projects on Oct. 20, eight days before he was fired from his OPM position and retired from his job as school constructi­on grants director.

A second request for documents containing certain “search” words made it clear federal authoritie­s were investigat­ing Diamantis’ oversight of the OSCG&R program and how it doled out state funding for school projects.

Diamantis’ team included at least four auditors and a supervisor, Robert Ficeto, who was copied on every audit, as were Diamantis and Dixon, the education consultant on the team, according to the Memorandum of Understand­ing created when Diamantis moved to OPM.

At the time the MOU was signed by then-DAS Commission­er Josh Geballe and then-Secretary of OPM Melissa McCaw, there were three vacancies on the audit team, which some municipal officials believe delayed the grants team from completing the audits on a more timely basis.

The audits were usually addressed to the DAS commission­er, which was initially Melody Currey but then shifted to Geballe after he assumed leadership of the agency in 2019.

However, a few were addressed directly to Diamantis. None were addressed to McCaw even though she oversaw Diamantis and the grant program until he was fired.

The audits are mostly formulaic – five- or six-page documents that list ineligible costs for every project – but in many cases give little detail as to their findings.

Some audits reference municipali­ties not giving contracts to the lowest bidder, but there is no indication of how the state responded, if at all, to that finding.

For example, a March 22, 2019 audit of the New Haven Amistad High School project noted that the Local Education Authority (LEA) didn’t utilize the lowest possible bidder without specifying who the contractor was or how much they were paid.

But a Feb. 1, 2019 audit of multiple Bridgeport school projects found that a $24,000 contract with an architectu­ral firm was not properly bid and the state wouldn’t pay the bill.

About a quarter of the audits indicated that bid documents were missing, some of which exceeded the state’s $50,000 no-bid threshold. And more than half of the audits listed “unsubstant­iated change orders,” meaning that state officials did not approve the change order and therefore the municipali­ty must cover the costs.

Anderson, the DAS spokeswoma­n, said once a local school board certifies a project has been completed, it has one year to file a report with OSCG&R, kick-starting the audit process.

A preliminar­y audit is then completed by OSCG&R and sent to the municipali­ty for review.