Northern Berks Patriot Item

Route 222 warehouse developers file second lawsuit

- By Keith Dmochowski kdmochowsk­i@readingeag­le.com

Maidencree­k Township is being sued for the second time in months by the developers of a proposed 930,000-square-foot warehouse, this time for failing to control the conduct and process of conditiona­l use hearings as required by state law.

The lawsuit, filed Feb. 17 in Berks County Court, references a series of hearings in which developer and property owner Maiden Creek Associates aims to prove the warehouse plans at Route 222 and Schaeffer Road meet certain conditions for land use in the township’s regional commercial district.

Conditiona­l use approval is needed before township supervisor­s can decide on final plan approval.

The suit claims that by permitting hours of crossexami­nation, township supervisor­s allowed the hearings to become out of control and unproducti­ve.

The hearings began in late November and are slated to continue through late March and beyond.

The suit references the cross-examinatio­n of Chris Williams, the developers’ traffic engineerin­g expert, during a January hearing when a residents’ group opposing the warehouse spent nearly three hours combing through details of a March traffic impact study.

It claims the questionin­g was “inappropri­ate, irrelevant, beyond scope, or used to present the opposition party’s case,” complaints that the developers’ attorney Gregg Adelman voiced during the January hearing.

At that time, Adelman threatened township officials with legal action if they continued to allow the lengthy questionin­g without limiting its scope or scheduling additional hearings to expedite the process.

Those complaints are solidified in the suit, which says that by failing to schedule more hearings — despite repeated requests by the developers — the board violated state rules requiring that conditiona­l use applicants be given sufficient time to present their case within 100 days of the initial hearing.

The most recent hearing Feb. 27 also featured a lengthy cross-examinatio­n of Williams.

The next hearing is scheduled for March 27, roughly four months from the initial hearing date.

At the hearing in January, township solicitor Eric Frey said the board wouldn’t set any limits on residents’ ability to ask questions.

“These are laypeople, not attorneys; we’re not going to limit their time,” Frey told Adelman at the time. “We have to consider their (residents’) due process rights to ask the questions they want to ask.”

Maidencree­k residents have since defended their right to question the developers.

“Something is seriously wrong with the developers’ data, and we have the right to question it,” resident Cliff Panneton wrote in a Feb. 9. letter to the Reading Eagle. “We were not filibuster­ing. We were seeking the truth.”

The developers claim their right to due process is being impeded by the supervisor­s’ choice to permit the lengthy questionin­g.

“As this is a matter of ongoing litigation, the amount of comment that the township will offer publicly will be limited. The board will continue to follow the guidance of its profession­als, its ordinances, state regulation­s, and statutes as we work toward the best interest of the residents.” — Stated in the release

The suit requests the court require the supervisor­s to schedule enough hearings for the developers to conclude their case by March 10 — the 100 day mark — or appoint an independen­t hearing officer to oversee and schedule the remaining proceeding­s.

If Maidencree­k cannot give developers time to complete their case by March 10, the suit requests the court approve the conditiona­l use applicatio­n on March 11.

The supervisor­s issued a press release saying that township leaders would review the claims made in the suit and respond appropriat­ely, “As this is a matter of ongoing litigation, the amount of comment that the township will offer publicly will be limited,” the release said. “The board will continue to follow the guidance of its profession­als, its ordinances, state regulation­s, and statutes as we work toward the best interest of the residents.”

The developers filed a complaint in January claiming the township’s noise ordinance makes it virtually impossible to build on the proposed warehouse site and is therefore illegal.

Maidencree­k officials gave no updates on that suit.

 ?? KEITH DMOCHOWSKI — MEDIANEWS GROUP ?? Plans for the 930,000-square-foot fulfillmen­t center
KEITH DMOCHOWSKI — MEDIANEWS GROUP Plans for the 930,000-square-foot fulfillmen­t center
 ?? KEITH DMOCHOWSKI — MEDIANEWS GROUP ?? A 930,000-square-foot warehouse, shown in this rendering, is proposed for 81 acres at Route 222and Schaeffer Road in Maidencree­k Township.
KEITH DMOCHOWSKI — MEDIANEWS GROUP A 930,000-square-foot warehouse, shown in this rendering, is proposed for 81 acres at Route 222and Schaeffer Road in Maidencree­k Township.

Newspapers in English

Newspapers from United States