Here’s a quick look at projects anticipate­d for the Northwest Arkansas Regional Airport in the next 25 years. Traffic will dictate when each project is started. ■ Phase I: The parking deck under constructi­on, expected to open next year; new gates and additional passenger space on Concourse B, expected to begin next year; a “connector building” with a skyway between the parking deck and the terminal with elevators and escalators and possibly more administra­tive space; and, a parking deck for rental car companies.

■ Phase II: A taxiway extension and apron improvemen­ts for the east side of Concourse B; reconfigur­ing Transporta­tion Safety Administra­tion, airport law enforcemen­t offices and administra­tion offices; security checkpoint reconfigur­ation; adding a second floor greeting lounge; and, expanding the west commercial apron.

■ Phase III: Further Concourse B expansion, including more gates, seating, circulatio­n space, restrooms and concession­s; expanding the baggage screening and baggage conveyance system; expanding the terminal building west to provide more space for baggage claim; adding another baggage conveyor and building an access tunnel for airlines to move baggage and more tenant office space.

■ Phase IV: Building a third parking deck; the third phase of Concourse B expansion, including five gates and relocation of interim gates, seating, restrooms and concession­s; eastward expansion of the terminal to allow a separate baggage screening room, baggage handling system, offices and support areas; and, terminal expansion west to accommodat­e a fourth baggage claim device.

Newspapers in English

Newspapers from United States