Northwest Arkansas Democrat-Gazette

Fort Smith authorizes $612,000 agreement for city pump station

- THOMAS SACCENTE

FORT SMITH — The Board of Directors on Tuesday authorized an agreement with Hawkins-Weir Engineers for providing constructi­on services for wastewater pump station flood damage repairs and mitigation.

The amount for the agreement is not to exceed $612,000.

Lance McAvoy, city utility director, wrote in a memo the 2019 Arkansas River flood, the utility department hired Hawkins-Weir to assess the damage to water and wastewater infrastruc­ture. The Van Buren-based firm was awarded the design contract for the flood damage repair and the mitigation work to restore and protect the city’s assets from future flooding.

This work, McAvoy said, included collaborat­ing with the constructi­on management company Van Horn Constructi­on of Russellvil­le to value engineer and expedite the work by using “constructi­on management at risk” to deliver the project in a way both efficient and financiall­y responsibl­e.

At the meeting Tuesday, McAvoy said constructi­on management at risk in this case essentiall­y means Van Horn takes on a certain amount of risk with the project.

“When the bids are put in, if something is found, if there’s an overrun, they end up eating that,” McAvoy said. “It doesn’t come back to the city. The only time that the city would amend the contract would be if we ask for something additional that wasn’t in the original contract.”

McAvoy wrote the city also hired Witt Global Partners to help with documentin­g and receiving reimbursem­ent from the Federal Emergency Management Agency associated with the recovery and mitigation. However, Witt Global discovered several flood damage repair items hadn’t originally been brought to Hawkins-Weir’s attention and weren’t in the scope of design outlined in the original agreement.

“When the bids are put in, if something is found, if there’s an overrun, they end up eating that. It doesn’t come back to the city.” — Lance McAvoy, Fort Smith utility director

At this point, McAvoy wrote the board has approved three of the five phases of the constructi­on management at risk project. The parts to begin the repairs, which are scheduled to begin in May, have been ordered. Utility Department staff recommende­d hiring Hawkins-Weir for constructi­on inspection and observatio­n. The additional design work will also be added to the new agreement to cover the items Witt Global discovered.

The additional design work, according to McAvoy, is estimated to cost $35,800. The associated constructi­on inspection and observatio­n for the entire project, which includes all five phases, is estimated to cost $576,200. This total amount is in the 2020 capital improvemen­t plan budget, with the expenses being considered a reimbursab­le item by FEMA.

Newspapers in English

Newspapers from United States