Northwest Arkansas Democrat-Gazette

Fort Smith officials hear department­s’ capital improvemen­t plans

- MONICA BRICH

FORT SMITH — Administra­tors are asking to spend $ 45 million over the next decade to upgrade the city’s Solid Waste Department.

City directors heard several capital plans during a study session Tuesday evening. Deputy City Administra­tor Jeff Dingman presented the Solid Waste Department’s plan, as he’s currently acting as its interim director.

Dingman said in a memo to the board the equipment replacemen­t schedule is regularly evaluated and can be adjusted due to equipment conditions or maintenanc­e requiremen­ts.

The equipment subtotal for the 2022 capital improvemen­t plan is almost $2.9 million and includes adding two front-load garbage trucks for residentia­l collection, one front-load garbage truck for commercial collection, a service truck and crew cab pickup for fleet maintenanc­e and a big bulldozer, an articulati­ng dump truck and crew cab pickup for the landfill.

Dingman said a couple of items, including a ground compactor, were lease-purchased over the last three years. He said the department intends to stop leasing and buy the equipment it needs through a replacemen­t program, keeping it as a frontline unit for its useful life, then having it as a reserve until it can be replaced.

The department also has a subsection project at the landfill, which brings next year’s total to $9,380,226. The subsection­s compact waste and help organize space.

Dingman said cell A-6 is the last subsection for phase A of the landfill, and the first cell for phase B is scheduled to be developed adjacent to the area before the landfill closes phase A. He said the department plans to develop a subsection around every five years afterward, which coincides with the cell’s operating life.

Dingman also discussed how the compressed natural gas conversion at the Solid Waste Department installati­on should be complete by the end of the year and available for use in early 2022. He said from this point forward, all of the department’s equipment will be replaced with natural gas-powered vehicles where available, especially the trucks that transport solid waste.

The city’s applicatio­n for the Diesel Emissions Reduction Act grant money from the federal Environmen­tal Protection Agency is pending, he said.

Dingman said if approved, the grant will pay two-thirds of the cost to replace up to 14 solid waste collection vehicles with natural gas-powered vehicles, and the 10-year schedule will be revised to

accommodat­e the accelerate­d replacemen­t.

He said the fueling station is being outfitted to service natural-gas vehicles. The department will buy natural gas vehicles anyway, because it will already have a fueling station.

“There still are likely to be three collection vehicles that are going to show up as diesel, because we ordered them before this process, and it takes 12 months at least to get these things, from the time you issue a purchase order until the time it shows up,” he said.

Utility Director Lance McAvoy also presented plans for various water systems maintenanc­e improvemen­ts. The plan is expected to cost roughly $332 million over the next 10 years.

The project subtotal for 2022 is about $34.2 million for water, $19.4 million for non-consent decree wastewater, and $36.3 million for consent decree wastewater.

Several projects relate to constructi­ng a second water transmissi­on line from Lake Fort Smith to the city should the first transmissi­on line fail.

Other 2022 projects include replacing aging water lines, painting and maintainin­g several water tanks and having the Arkansas Department of Transporta­tion do overlay, sidewalk and drainage improvemen­ts on Towson Avenue to reduce traffic disruption­s associated with needing to access the utilities under the street.

McAvoy said the total project costs for 2022 is roughly $90 million, due to supply chain issues including increasing material costs.

Several directors discussed their concerns with approving the plan if there’s projects the city will have to postpone due to rising costs.

“You’re right, it only makes sense to do the absolute required projects, and we do have a lot of those, actually,” City Administra­tor Carl Geffken said.

“The transmissi­on lines, that’s the first that comes to mind. So we’ll have to think strategica­lly and be able to spend the money we have prudently so we don’t just go off and say what we think is $34 million for water could be $68 million. This is the plan with our estimate of what the cost can be, should be, but of course reality will dictate whether we can do it all or not. But this is our plan on what we would like to see done, if at all possible.”

 ?? (NWA Democrat-Gazette/e/Hank Layton) ?? Equipment operator Zac Dwyer loads waste Friday into a garbage truck driven by Roman Williams in a residentia­l neighborho­od in south Fort Smith. The city’s Board of Directors is preparing to approve annual budgets, which may include several new trucks for the Solid Waste Department. Go to nwaonline.com/211031Dail­y/ to see more photos.
(NWA Democrat-Gazette/e/Hank Layton) Equipment operator Zac Dwyer loads waste Friday into a garbage truck driven by Roman Williams in a residentia­l neighborho­od in south Fort Smith. The city’s Board of Directors is preparing to approve annual budgets, which may include several new trucks for the Solid Waste Department. Go to nwaonline.com/211031Dail­y/ to see more photos.
 ?? (NWA Democrat-Gazette/Hank Layton) ?? A garbage truck driven by Gustavo Garcia unloads waste Friday at the Fort Smith landfill. Go to nwaonline.com/211031Dail­y/ to see more photos.
(NWA Democrat-Gazette/Hank Layton) A garbage truck driven by Gustavo Garcia unloads waste Friday at the Fort Smith landfill. Go to nwaonline.com/211031Dail­y/ to see more photos.

Newspapers in English