Orlando Sentinel

Builder: I-4 Ultimate eight months behind

Highway project also $100 million over its budget

- By Kevin Spear Staff Writer

Interstate 4’s overhaul will run eight months beyond a scheduled finish in early 2021 and $100 million over a $2.3 billion budget, according to a recent claim by the builder.

Neither the builder, I-4 Mobility Partners, nor the state Department of Transporta­tion previously had publicly disclosed a potential change in schedule or budget.

Details first emerged from Moody’s Investors Service, with reports on I-4 Mobility’s financial footing.

The state Department of Transporta­tion issued a statement on Thursday, emphasizin­g that the I-4 Mobility Partners claim remains undetermin­ed.

“While the claim is being reviewed, constructi­on activities are continuing and the contractor is being held to the terms of the contract with the original completion dates set forth in the agreement,” department spokesman Steve Olson said.

“No time extensions or financial considerat­ions have been granted to the contractor from FDOT,” Olson said.

Moody’s reported on June 28 that it had posted a negative outlook for three loans totaling $1.4 billion taken on by I-4 Mobility Partners.

Called I-4 Ultimate, the massive remake of the 60-year-old freeway began in 2015.

The project will add toll lanes along a 21-mile section of I-4 from north of State Road 434 in Seminole, through Orlando and

to west of Florida’s Turnpike in Orange County.

I-4 Ultimate is a “publicpriv­ate partnershi­p,” in which the builder and the state are co-investors in a road expected to generate revenue through tolls.

While motorists may face an added eight months of constructi­on on I-4, a road now widely detested by many drivers, what the $100 million claim may mean for taxpayers was not immediatel­y clear.

Neither the Florida Department of Transporta­tion nor I-4 Mobility Partners responded to requests for an interview.

I-4 Mobility Partners issued a statement, saying “a project of this size and complexity will nearly always encounter unexpected challenges.”

An ongoing challenge for the financial viability of the project, according to Moody’s, is “21 miles of reconstruc­tion in a congested urban corridor, where constructi­on activities will be constraine­d by the need to maintain existing traffic.”

A Moody’s “Credit Opinion” report of June 29 noted that the builder and transporta­tion department are likely to hold discussion­s in coming months.

“The contractor­s have already had extensive workshops and schedule meetings to try to re-sequence work and find efficienci­es in the schedule,” the report further states, adding that some strategies may reduce work by as many as 100 days.

According to further detail disclosed by Moody’s, schedule slippage had been noted through the last half of last year.

Potential fluctuated from as few as 130 days to as many as 188 days by the year’s end.

By March, the potential delay had increased to 245 days, or nearly eight months.

On June 11, I-4 Mobility Partners filed its claim for $100 million in additional compensati­on and for a 245-day time extension, according to Moody’s.

The state’s transporta­tion department has 120 days to review the claim.

The Moody’s report stated “The delay is primarily due to a catastroph­ic drilled shaft failure” in the downtown Orlando portion of the interstate.

Two such failures occurred in attempts to construct foundation­s, according to Moody’s.

The builder blamed “complex geological conditions” and design for the failures.

Also cited by Moody’s were flooding and lane closures in March and May that prompted the state’s transporta­tion department to assess nearly enough “noncomplia­nce points” to declare I-4 Mobility Partners in default in the project.

Moody’s stated that the total of three worker fatalities so far in the I-4 Ultimate project is “atypical.”

Moody’s said that considerin­g the claim for more money and time, and the high number of noncomplia­nce points, “the importance of a cooperativ­e working relationsh­ip…is deemed critical at this time.”

The I-4 Mobility Partners statement said its “team will continue to work together with our partners at the Florida Department of Transporta­tion on solutions to address items that arise, with the aim of successful­ly delivering a state-of-the-art highway.”

 ?? SARAH ESPEDIDO/STAFF PHOTOGRAPH­ER ?? The pedestrian bridge over Interstate 4 at Colonial Drive was scheduled to be completed next spring. The entire I-4 Ultimate project, a six-year overhaul, needs an extra 8 months and $100 million, the builder says.
SARAH ESPEDIDO/STAFF PHOTOGRAPH­ER The pedestrian bridge over Interstate 4 at Colonial Drive was scheduled to be completed next spring. The entire I-4 Ultimate project, a six-year overhaul, needs an extra 8 months and $100 million, the builder says.
 ?? JACOB LANGSTON/STAFF PHOTOGRAPH­ER ?? The I-4 Ultimate project has caused traffic delays along the interstate itself, but it has also been a pain for drivers on cross streets near the highway, including this temporary closure of Colonial Drive in April because of bridge work by constructi­on crews.
JACOB LANGSTON/STAFF PHOTOGRAPH­ER The I-4 Ultimate project has caused traffic delays along the interstate itself, but it has also been a pain for drivers on cross streets near the highway, including this temporary closure of Colonial Drive in April because of bridge work by constructi­on crews.

Newspapers in English

Newspapers from United States