Pea Ridge Times

Wastewater treatment plant nears completion

- ANNETTE BEARD abeard@nwadg.com

Turning the switch to activate the new wastewater treatment plant is about six weeks away, if all goes as planned.

The plant will be operationa­l by mid-September, according to Water Utilities superinten­dent Ken Hayes. The 18-month project was delayed slightly by continuous rain this spring, but should be online soon, Hayes said.

“It’s been a long process, but we’re getting there,” he said.

The plant is a simultaneo­us nitrificat­ion denitrific­ation activated sludge plant and should handle a million gallons a day.

“The simultaneo­us nitrificat­ion denitrific­ation makes the plant quite a bit more complicate­d because of getting nitrogen out,” Hayes said.

The current plant, constructe­d in the 1980s, is essentiall­y the first plant for the city, Hayes said. “Before that, there were two sewer ponds.”

According to newspaper records, the Arkansas Department of Pollution Control and Ecology granted a permit to Pea Ridge for constructi­on of a new sewer plant in July 1979. City ordinance 130 authorized improvemen­ts and repairs to the current treatment plant; it was approved in 1984.

Former city employee Ron David (who worked for the city from 1980 to 1994) said there was a double lagoon system before the plant was built in the early 1980s.

“The old plant got us 30 years,” Hayes said. It’s capacity is 300,000 gallons a day max and

“This will be a high tech plant with sensors.”

Ken Hayes

Superinten­dent

Pea Ridge Water Utilities Dept.

it’s currently pumping 370,000 gallons a day. The new plant will have a capacity of a million gallons a day.

The new plant was originally estimated to cost over $8 million, but the final cost, Hayes said, will be $7,970,000 and will include a $7,000 per month savings thanks to low interest rates.

The city’s Water Utilities Department serves more than 3,000 customers with the latest numbers of 3,119 water customers and 2,308 wastewater customers, according to records at the Water Utilities Department. There were 1,882 sewer customers in December 2016, and 2,132 in December 2018.

In June of 2018, city officials were notified that the plans for the new plant were in Little Rock awaiting approval from the Arkansas Health Department and the Arkansas Department of Environmen­tal Quality.

Bids were approved during a special meeting Dec. 4, 2018.

Ground was broken in March 2019.

“It took three years to get it engineered,” Hayes said, “way longer than they typically take.”

The new plant includes a half million dollars worth of electrical work, Hayes said, explaining that the bulk of the work is being done now.

“It’s a ‘racetrack’ with the wastewater going from the first cell to the second cell then to the clarifier,” Hayes said, explaining that the clarifier removes sludge — either waste activated sludge or return activated sludge, some of which is returned to the wastewater to keep the bug activity going.

“What’s wasted will go into the two ponds on the right, that’s basically sludge storage. The other side will be rainwater redundancy,” he said. “It’ll automatica­lly bypass the plant.”

“Because Pea Ridge is so flat — then, you’ve got all your outlying areas,” Hayes said of the water runoff from rain. “When the drainage gets so bad, it’s just going in the manholes so we get hammered.

“On a rain that’s not so bad, it doesn’t do much, but on a big rain, it’ll come in here for three days. It’s just geography.”

In the clarifier, all the “heavy stuff falls down,” he said. Basically, as it’s “stirred” with an arm like a squeegee, the bottom and the top layers are separated and removed.

“Once it comes to the clarifiers, then it’s sent to different locations for filtering and disinfecti­ng… there’s a lot to it,” he said.

“This will be a high tech plant with sensors; it’ll save money as well,” Hayes said.

Current employee Jake Wagner has been training and has earned his wastewater 3 license.

“We’re kind of lucky because Jake is pretty good at it,” Hayes said. He said Wagner has been training at the Rogers plant as it’s fairly similar to the Pea Ridge plant.

“We’ve needed this for years,” Hayes said. “It was way over due.”

 ?? TIMES photograph­s by Annette Beard ?? A clarifier separates sludge in the wastewater.
TIMES photograph­s by Annette Beard A clarifier separates sludge in the wastewater.
 ??  ?? Digging out bedrock so pump stations can be built, chunks of limestone called shot rock are broken loose, Ken Hayes said, and will be given to the city Street Department.
Digging out bedrock so pump stations can be built, chunks of limestone called shot rock are broken loose, Ken Hayes said, and will be given to the city Street Department.
 ??  ?? Limestone bedrock underlies the area where the city’s new wastewater treatment facility is being built.
Limestone bedrock underlies the area where the city’s new wastewater treatment facility is being built.
 ??  ?? A pump station is part of the treatment plant.
A pump station is part of the treatment plant.

Newspapers in English

Newspapers from United States