Township’s OK allows work at school, stadium

- By Margaret Smykla

The Upper St. Clair commission­ers on Monday granted a request by the school district for a conditiona­l use that will allow for the renovation of the high school natatorium and constructi­on of a 47½-foot-high community complex building at the high school stadium.

The R-1 single-family residentia­l district permits structures up to 35 feet. A 12½-foot modificati­on in the code requiremen­ts was needed for the new structure, which is planned to have three stories and a rooftopdec­k.

The district also sought permission to construct a 13foot retaining wall near the new building. The requests wereapprov­ed in a 5-1 vote.

During last month’s public hearing, Chuck Hokanson, whose Blairmont Drive home is 150 feet from the proposed new building, expressed concerns about losing his view of the valley, a loss of privacy as the windows of the facility will face his house and a decline in his property value.

“I am strongly opposed to the project,” he said at Monday’s public hearing about the new building, but he said he supports the new, eightlane swimming pool at the high school. He submitted a petition with more than 30 signatures from neighbors opposed to the building but favoringth­e pool.

Blairmont Drive resident Marty Kaplan said he enjoys walking in the neighborho­od and is concerned about the impact on the scenery and on property values.

The most affected residences in the neighborho­od would be six homes on Blairmont Drive, according to the district’s architect, Dave McLean of McLean Architects.

Mike Mudry of the Upper St. Clair Swim Club spoke in favor of the swimming pool project. “We’re here to support the entire package,” he said.

The project is part of a $16 million total capital plan approved by the school board earlier this year. In addition to the pool renovation, which will replace the existing five-lane pool built in 1961, it also includes completion of the Boyce Middle School field a multi-use complex at the high school stadium and related site improvemen­ts.

Those improvemen­ts include repairs to the bleachers, restroom upgrades, and improvemen­ts to the ticket booth, concession area and announcing­equipment.

Commission­er Ronald Pardini voted no. Commission­er Russell Del Re abstained, noting that his employer, PJ Dick Inc., was hired as constructi­on manager for the projects.

After the meeting, board President Mark Christie saidwith the larger building, the district was able to get the additional features it desired with a minimal impact onthe neighborho­od.

The district plans to begin constructi­on in the spring, with completion in August 2019.

 ??  ??