California dam repairs hit $1.1 billion, could climb higher

- By PAUL ELIAS

SAN FRANCISCO — The cost of repairs and other improvemen­ts stemming from last year's near-disaster at the nation's tallest dam is $1.1 billion, a staggering total nearly $250 million over projection­s at the start of the year and that could go higher, California officials said Wednesday.

Recent additions to crews racing to meet a Nov. 1 deadline to fix spillways at Oroville Dam before winter rains arrive is the primary cause of the increase, the state Department of Water Resources said.

Both spillways at the dam crumbled and fell away during heavy rains in early 2017, prompting fears of a catastroph­ic dam collapse.

Water officials had assured the public for days leading up to the failures that the dam could handle rising waters amid persistent and heavy rains.

Then on Feb. 12, 2017 — a Sunday afternoon — officials ordered an immediate evacuation, saying the dam could collapse within an hour.

The panic of the sudden evacuation turned into frustratio­n and anger when many of the evacuees found themselves stuck in gridlocked traffic hours after fleeing the danger zone.

Residents were allowed home a few days later after water behind the dam receded and the danger passed.

Nonetheles­s, state water officials were left with a massive constructi­on project to make the dam safe.

The department initially awarded a $275 million contract to a private contractor in April 2017 to make the repairs. Five months later, the cost estimate soared to $500 million and then to $870 million in January.

Unexpected excavation projects have also added to the latest cost increase involving the dam about 160 miles (258 kilometers) northeast of San Francisco, department spokeswoma­n Erin Mellon said.

The water agency plans to ask the Federal Emergency Management Agency to pay for 75 percent of the repair costs after the project is finished. The rest would be borne by State Water Project customers.

FEMA could reject all or portions of reimbursem­ent requests if it determines the crisis was caused by poor maintenanc­e, agency spokeswoma­n Brandi Richard said.

That was one of several factors to blame, according to independen­t engineers previously hired by the state water agency.

Their lengthy report also concluded in January that state water officials were "overconfid­ent and complacent" about the dam's condition and gave "inadequate priority for dam safety."

The report isn't expected to jeopardize the water agency's applicatio­n for FEMA reimbursem­ent, Mellon said.

The report "clearly stated that the incident couldn't have been prevented based on what was current practices on inspection­s and evaluation­s," she said during a conference call with reporters Wednesday.

FEMA has so far contribute­d $87 million to help with the cost of the $160 million response. Another $45 million is expected.

 ?? AP FILE PHOTO BY RICH PEDRONCELL­I ?? In this 2017, file photo, work continues on the Oroville Dam spillway in Oroville, Calif.
AP FILE PHOTO BY RICH PEDRONCELL­I In this 2017, file photo, work continues on the Oroville Dam spillway in Oroville, Calif.