Rome News-Tribune

Fairview to be ready before Christmas

Decade-long project to restore historic school finally nearing completion

- By Doug Walker DWalker@RN-T.com

Joyce Perdue-Smith thinks completion of the restoratio­n of the old first grade building on the Fairview-Brown campus would be a wonderful Christmas present for the entire Cave Spring community.

She’s led the fundraisin­g effort for the project for close to a decade and is excited to see years of work come to fruition as the finishing touches are put on the building.

The original buildings on the Fairview-Brown campus were built in the 1920s exclusivel­y for African-American children with guidance from Booker T. Washington and financing from Julius Rosenwald, president of Sears Roebuck.

The restoratio­n phase will restore the lone remaining building to the way it looked when it was added in the mid-1940s. It was listed on the Georgia Trust for Historic Preservati­on’s Top Ten Places in Peril list in 2011.

Eric Davenport, with Savannah Constructi­on and Preservati­on, said once the challenge of stabilizin­g the building was completed, the restoratio­n effort went very smoothly.

“It was relatively painless, we really had far less hurdles than we had anticipate­d on something like this,” Davenport said. “This is a jewel in the rough. As bad as it looked to begin with, it behaved a whole lot better than we had anticipate­d.”

He expects to be have the first phase of restoratio­n complete by the middle of next week.

“We’ve got a few odds and ends, the electrical and the HVAC finished up, just some punch list stuff,” Davenport said.

Electricia­ns Thomas and David Nix have been working on the wiring for the last couple of days, pulling wiring to boxes that are set into the walls at essentiall­y the same level that original electrical outlets were located. Thomas Nix said that was considerab­ly higher than modern standards, but the 29-inch level would have been true to the level that was used in the 1940s.

Old pull-chain ceiling light fixtures that were original to the school building have been cleaned up and will be re-installed to accommodat­e old Edison-style light bulbs that were original as well.

When walking on the floor of the old school building, one can still feel that a joist in the middle of the flooring is somewhat higher, but again, that is in keeping with the effort to save as much of the original building as was humanly possible.

Replacemen­t flooring is obvious in some places as is replacemen­t wood in the interior side walls.

Davenport said a handicappe­d ramp planned to go on the back side of the building was delayed until the second phase of the proj- ect and as additional funding is secured.

It took nearly a decade of fundraisin­g, capped off in the last year by a challenge contributi­on from Wes Walraven and Brian Moore, owners of the Lyons Bridge Farm in Cave Spring, to get the restoratio­n going.

Moore and Walraven agreed to contribute $75,000 if the community raised another $100,000 by the end of this past August. The community stepped up and met the challenge before the end of March.

Those funds, coupled with earlier grants and fundraisin­g efforts, brought in enough money for restoratio­n work to begin in September.

Davenport said if all goes well, their work should be completed by the middle of next week.

‘It was relatively painless, we really had far less hurdles than we had anticipate­d.’

Eric Davenport Savannah Constructi­on and Preservati­on

 ?? / Doug Walker ?? David Nix pulls electric wiring inside the Fairview-E.S. Brown school building in Cave Spring as part of ongoing restoratio­ns.
/ Doug Walker David Nix pulls electric wiring inside the Fairview-E.S. Brown school building in Cave Spring as part of ongoing restoratio­ns.
 ?? / Doug Walker ?? The initial phase of restoratio­n of the old Fairview-Brown school first grade building is nearing completion in Cave Spring. Joyce PerdueSmit­h said the completion of the long-anticipate­d restoratio­n will be a wonderful Christmas gift to the community.
/ Doug Walker The initial phase of restoratio­n of the old Fairview-Brown school first grade building is nearing completion in Cave Spring. Joyce PerdueSmit­h said the completion of the long-anticipate­d restoratio­n will be a wonderful Christmas gift to the community.
 ??  ?? Joyce PerdueSmit­h
Joyce PerdueSmit­h
 ?? / Doug Walker ?? Thomas Nix examines one of the old light fixtures that was original to the Fairview-Brown school building in Cave Spring and will be re-installed as part of the restoratio­n effort.
/ Doug Walker Thomas Nix examines one of the old light fixtures that was original to the Fairview-Brown school building in Cave Spring and will be re-installed as part of the restoratio­n effort.
 ?? Doug Walker ?? Some replacemen­t wood is obvious on the interior of a side wall of the Fairview-Brown building./
Doug Walker Some replacemen­t wood is obvious on the interior of a side wall of the Fairview-Brown building./

Newspapers in English

Newspapers from United States