San Francisco Chronicle

Transbay builder has to pay for fixes

- By Michael Cabanatuan

The cost of repairing the Transbay Transit Center, a task that is likely to take weeks and cost millions, will be covered by warranty, officials confirmed Wednesday.

The general contractor or its subcontrac­tors are responsibl­e for repairing any constructi­on flaws, not the center’s operator, the Transbay Joint Powers Authority.

That is one of the few certaintie­s or easy answers about the broken transit

hub, which has been shut down since the discovery of cracks in two critical support girders on Sept. 25, six weeks after it opened.

The damaged section of the $2.2 billion transit center, over Fremont Street, has been stabilized, and constructi­on crews plan to erect temporary support towers on three levels of the structure this week. But until that work is done, engineers can’t complete tests to determine the cause of the cracking and devise a fix.

Repairs likely will be costly. Asked for a rough estimate after a meeting of the authority Tuesday, Executive Director Mark Zabaneh shrugged and said: “Thousands? Millions?”

Whatever the cost, he said Wednesday, “The transit center is under warranty for two years and once we determine the cause of this, we will make sure the proper entity is held responsibl­e.”

The Transbay JPA’s agreement with general contractor Webcor/ Obayashi requires it to correct substandar­d work “at no cost to the TJPA for a period of two years after substantia­l completion.”

The contract states that the contractor “shall warrant and guarantee the work against defects in materials and workmanshi­p for 24 months” and that work will be “free of any defect of equipment, material and installati­on.”

The warranty calls for the contractor to promptly “remove, replace or correct work ... which is damaged or found defective” upon written notice, and allows the TJPA to do the work itself, at the contractor’s expense, if it’s not fixed “within a reasonable time.”

It also says: “The contractor shall warrant and guarantee the work against defects in materials and workmanshi­p for 24 months.”

The Transbay Transit Center opened Aug. 12 after nearly eight years of demolition and constructi­on. A certificat­e of occupancy has been issued but work is not complete. Workers are still installing public art, lighting and sidewalks in Shaw Alley near the complex as well as trim around some of the center’s ceiling tiles.

It was during that ceiling work that the fissures in the first steel girder were discovered. Transbay officials quickly shut down the center — “out of an excess of caution,” they said — as well as Fremont Street where it passes under the building.

Transbay officials say they could reopen Fremont Street, a major route into downtown San Francisco from the Bay Bridge, this week — but certainly

“We will make sure the proper entity is held responsibl­e.” Mark Zabaneh, executive director, Transbay Joint Powers Authority

by Oct. 12 — when the temporary support towers are installed.

After that occurs, forensic engineers can take samples from the damaged steel beams and scrutinize them to determine the cause of the cracking — a process that should take about two weeks.

Designing a fix for the problem, and getting it reviewed by an independen­t committee of outside engineers, design and metallurgy experts will take weeks more. Then, finally, constructi­on workers can repair the problem, which will likely involve adding material to strengthen the damaged beams, said Dennis Turchon, senior constructi­on manager.

Zabaneh said it’s too early to put a target date on reopening the center to buses and commuters because the extent of repairs is still uncertain. But the popular 5.4-acre rooftop park could reopen in early November.

 ?? Scott Strazzante / The Chronicle ?? Hydraulic jacks help support the new Transbay center above Fremont Street in San Francisco where cracks in girders were discovered and must be fixed.
Scott Strazzante / The Chronicle Hydraulic jacks help support the new Transbay center above Fremont Street in San Francisco where cracks in girders were discovered and must be fixed.

Newspapers in English

Newspapers from United States