San Francisco Chronicle

No Central Subway until 2022 at earliest

Progress on Chinatown route delayed by pandemic ‘ and other complexiti­es’

- By Michael Cabanatuan

Muni’s Central Subway, once scheduled to run beneath downtown San Francisco to Chinatown by the end of 2018, won’t start carrying passengers until at least spring of 2022.

The most recent delay was blamed on the coronaviru­s “and other complexiti­es,” according to a post on the Municipal Transporta­tion Agency’s website. The opening most recently had been scheduled for mid2021.

But the coronaviru­s pandemic has slowed progress on the subway. Tom Maguire, the agency’s deputy director, said large constructi­on crews who often work shoulder to shoulder had to be quarantine­d after three separate outbreaks of the coronaviru­s. Delivery of materials and equipment was delayed, with many suppliers shut down or slowed by coronaviru­s

restrictio­ns.

Muni officials and politician­s broke ground for the 1.7mile subway in 2010 and for the first several years the project remained on schedule and budget. But conflicts with contractor Tutor Perini, troubles with unexpected soil conditions and a problem when a subcontrac­tor installed the wrong type of rail pushed the 2018 opening back to 2019 and then the middle of next year.

With fewer people riding Muni and problems with overhead power cables in the Metro subways, all rail service has been halted until at least early next year. Still, the continued delays on the subway project are bothersome, Maguire acknowledg­ed.

“It is frustratin­g,” he said. “We made the decision to build the Central Subway long before COVID, and it was the right project, bringing subway service to Chinatown and the most congested part of the city. And it’s still the right project,” he said. “But every day we don’t deliver service is another day we’re not serving our customers.”

Maguire said the agency settled disputes with the contractor through September 2019, and the subway’s cost has increased to $ 1.6 billion, up from $ 1.5 billion originally, and is likely to continue to grow with the coronaviru­s delays. Despite the repeated slowdowns, constructi­on is about 97% complete, Maguire said, with workers mostly putting on the finishing touches — things like glass elevator doors and fixtures on the walls.

So why will it take until 2022 to catch a subterrane­an transit ride to Chinatown? Once constructi­on is completed, possibly in March, the contractor will turn over the subway to the transit agency, which will spend about a year testing everything from fire alarms and ventilatio­n systems to the computeriz­ed train control systems to make sure it all works properly. The subway’s systems also need to be certified by regulators.

“Heavy constructi­on projects in San Francisco are so complicate­d and take such a long time,” Maguire said. “That’s no excuse, but it is a factor.”

Supervisor Aaron Peskin, who represents Chinatown, acknowledg­ed the complexity of building beneath the densest part of the city but said he is fed up with the continual delays and the agency’s failure to announce them in a timely manner.

“I get the fact that major projects like this are complicate­d and take a long time and sometimes come in late,” he said. “But this is an abject embarrassm­ent.”

The delays have not only slowed the arrival of highcapaci­ty transit to Chinatown, one of the nation’s densest neighborho­ods, but the protracted constructi­on has also driven customers away from some Chinatown businesses. The city has offered financial assistance to affected businesses.

Peskin said the transit agency should have been better at projecting constructi­on times, more transparen­t in acknowledg­ing delays and quicker to announce them.

“They’ve run out of excuses,” he said. “It’s not like I can go down there with my hammer and nails and make things go faster, but this is unconscion­able.”

Newspapers in English

Newspapers from United States