Santa Cruz Sentinel

‘Nothing but problems’: Tear-down of shipwreck enters fifth month

- By Russ Bynum

SAVANNAH,GA.>> When salvage crews began cutting apart the capsized Golden Ray, a shipwreck the size of a 70-story office building with 4,200 cars within its cargo decks, in early November they predicted the demolition could be wrapped up by New Year’s Day.

Four months later, the job remains far from finished.

Both ends of the cargo ship have been cut away and carried off by barges in a pair of giant chunks. But roughly three-fourths of the vessel remains beached on its side off St. Simons Island on the Georgia coast, where the South Korean freighter overturned soon after leaving port Sept. 8, 2019.

“It’s been nothing but problems out here,” said Andy Jones, a St. Simons Island resident who heads to the wreck site in his small fishing boat most days to monitor the demolition and post updates to a YouTube channel. “It’s a disappoint­ingly slow pace.”

Salvage experts decided more than a year ago that the Golden Ray, measuring 656 feet long, was too big to remove intact. They settled on a plan to carve the ship into eight massive chunks, each weighing up to 4,100 tons.

They straddled the wreck with a towering crane with a winch and pulley system attached to 400 feet of anchor chain that acts as a dull sawblade, tearing through the ship’s hull with brute force.

Start-to-finish, each individual cut was supposed to take a single day. Taking into account time needed to load each severed ship section onto a barge and

prepare for the next slice, the multiagenc­y command overseeing the effort predicted the job would take eight weeks.

It’s turned out to be a lot harder.

The first cut began Nov. 6 and took three weeks. Lifting the ship’s bow section revealed battered cars and SUVs in neat, layered rows on the interior decks. The second cut started a month later, on Christmas Day, and was finished in a week.

Crews spent the entire month of February attempting a third cut through the ship’s engine room, a section fortified with thicker steel. After strain on the cutting apparatus forced extensive maintenanc­e, the salvage crew stopped with the cut only about half finished.

They spent days moving the crane to the other end of the ship, where they began cutting a new section May 7 while rethinking

plans to complete the unfinished one.

The ship’s steel has proven tougher than anticipate­d, slowing the process, and crews have taken pauses to perform extra inspection­s and maintenanc­e, said Coast Guard Petty Officer 2nd Class Michael Himes, a spokesman for the multiagenc­y command overseeing the demolition.

“If people are wondering when it is going to be done, we’re doing it as quickly and as safely as can be done,” Himes said. “But quick takes a back seat to safety.”

He said it’s possible the last chunk of the ship could head to the scrapyard by June, the first month of the Atlantic hurricane season. Workers have taken steps to make the cutting more efficient, using torches to remove strips of the ship’s hull plating and form a guide for the cutting chain. They’re also using a big mechanical claw to pluck cars from inside the ship to shed weight before sections are cut and lifted.

 ?? ST. SIMONS SOUND INCIDENT RESPONSE PHOTO BY FARRELL LAFONT OF GALLAGHER MARINE SYSTEMS ?? A towering crane straddles the capsized cargo ship Golden Ray, its interior decks exposed after the ship’s bow was cut off and hauled away, off the coast of St. Simons Island, Ga.
ST. SIMONS SOUND INCIDENT RESPONSE PHOTO BY FARRELL LAFONT OF GALLAGHER MARINE SYSTEMS A towering crane straddles the capsized cargo ship Golden Ray, its interior decks exposed after the ship’s bow was cut off and hauled away, off the coast of St. Simons Island, Ga.

Newspapers in English

Newspapers from United States