Santa Fe New Mexican

WIPP planning to expand site

Workers to carve more space out of salt bed, set to finish in 2020

- By Susan Montoya Bryan DAVID X. TEJADA/U.S. DEPARTMENT OF ENERGY VIA AP

ALBUQUERQU­E — Workers are expected to begin mining operations at the Waste Isolation Pilot Plant in southeaste­rn for the first time in three years following a radiation release that contaminat­ed part of the undergroun­d repository, the Energy Department said Tuesday.

The work to carve out more disposal space from the ancient salt formation where the repository is located will begin later this fall and should be completed by 2020, the department said in a statement.

Workers will remove more than 112,000 tons of salt, making way for seven disposal rooms. Each will have space for more than 10,000 drums containing up to 55 gallons of waste.

The repository began accepting shipments of radioactiv­e waste from defense sites and national laboratori­es earlier this year after being closed for nearly three years.

It’s working to catch up with the nation’s multibilli­on-dollar program for cleaning up tons of waste left behind by decades of bombmaking and nuclear research. The waste includes radioactiv­e tools, gloves, clothing and other debris.

The pace of shipments is increasing slowly, but federal auditors recently raised concerns that the repository could run out of space. The U.S. Government Accountabi­lity Office also found that the Energy Department has no plans for securing regulatory approvals and expanding the Waste Isolation Pilot Plant before it reaches capacity in less than a decade.

Mining for the new disposal area first began in 2013 but was halted after the radiation release in February 2014.

A chemical reaction inside a barrel of waste that was inappropri­ately packed at Los Alamos National Laboratory before being shipped to the Southern New Mexico repository was blamed for the radiation release.

Twenty-two workers at the repository were exposed, and monitors at the surface recorded low levels of radiologic­al contaminat­ion. Officials maintained that nearby communitie­s were not at risk.

The incident resulted in a $74 million settlement

with the state of New Mexico for numerous permit violations at both the lab and the repository.

Investigat­ors said the misstep could have been avoided if existing policies and procedures had been followed.

The settlement, signed in early 2016, was at the time the largest ever negotiated between a state and the Energy Department.

Since then, some areas of the repository have remained offlimits, making it impossible for crews to do maintenanc­e to prevent its ever-shifting salt ceilings and walls from collapsing.

In one area, monitors last month picked up on increased movement, indicating some instabilit­y. A rock fall in November 2016 forced a brief evacuation of workers but there were no injuries or contaminat­ion.

As the mining work resumes, officials said crews will install rock bolts to provide stability inside the new disposal vault.

A machine called a continuous miner removes the salt. It’s loaded into a large truck and then a hoist that carries the material nearly a half-mile to the surface.

 ??  ?? A machine called a continuous miner operates at the Waste Isolation Pilot Plant near Carlsbad. The U.S. Energy Department announced Tuesday that the work to carve out more disposal space from the ancient salt formation will begin later this fall.
A machine called a continuous miner operates at the Waste Isolation Pilot Plant near Carlsbad. The U.S. Energy Department announced Tuesday that the work to carve out more disposal space from the ancient salt formation will begin later this fall.