Santa Fe New Mexican

Audit cites flaws, poor management in costly California bullet train project

- By Don Thompson

SACRAMENTO, Calif. — Flawed decision-making and poor contract management contribute­d to billions in cost overruns and years of delays in the as-yet unbuilt California’s high-speed rail line between Los Angeles and San Francisco, state auditors said Thursday.

The project is now estimated to cost $77 billion and is 15 years from completion.

State Auditor Elaine Howle faulted the California High-Speed Rail Authority for starting limited constructi­on in 2013 before it completed critical tasks like buying land, relocating utilities or obtaining agreements from outside groups, including local government­s and other railroad operators.

That led to numerous contract changes, project delays and overruns that have led to a nearly doubling of the original cost estimate of $40 billion.

The audit cited more than $2 billion in current or expected contract changes on three active Central Valley projects that were expected to cost about $3 billion. Meanwhile, delays have pushed completion estimates on those projects from this year to 2022.

Republican Assemblyma­n Jim Patterson of Fresno sought the audit with Democratic Sen. Jim Beall of San Jose.

“Insurmount­able funding shortfalls, continued mismanagem­ent and hugely flawed assumption­s mean this project is dead in the water,” Patterson said. “There will never be a completed track from the Bay Area to Los Angeles. … The best we can hope for is a rump railroad running from Bakersfiel­d to Madera.”

The project, backed by thenGov. Arnold Schwarzene­gger and approved by voters in 2008, has been the subject on many lawsuits and strident opposition from Republican­s and some Democrats, who see it as an unnecessar­y money pit.

But Gov. Jerry Brown has been steadfast with his support even as costs ballooned and the completion estimate drifted past the 2029 target.

Gov.-elect Gavin Newsom, a fellow Democrat, was strongly for it in 2008, turned lukewarm later as costs rose and now says he supports it but is concerned there’s no plan in place to pay for the increased cost.

The audit criticized the project’s convoluted management system in which 56 people manage hundreds of contracts worth more than $5 billion, yet just three contract managers have that role full time and there is high turnover and little oversight of the others.

Many of the others are outside consultant­s who “may not have the best interests of the state as their primary motivation,” auditors said, noting that the authority often “relied on the contractor­s’ own estimates and projection­s of the associated costs and delays.”

It recommende­d hiring fullstime, experience­d state employees to manage the contracts.

 ?? ASSOCIATED PRESS FILE PHOTO ?? A full-scale mock-up of a high-speed train is displayed at the Capitol in Sacramento, Calif. An audit released by the state auditor faults the High-Speed Rail Authority for starting constructi­on of the project before it completed critical planning for what has grown to be a $77 billion bullet train.
ASSOCIATED PRESS FILE PHOTO A full-scale mock-up of a high-speed train is displayed at the Capitol in Sacramento, Calif. An audit released by the state auditor faults the High-Speed Rail Authority for starting constructi­on of the project before it completed critical planning for what has grown to be a $77 billion bullet train.

Newspapers in English

Newspapers from United States