ALBUQUERQU­E — State regulators are close to deciding whether to approve an applicatio­n by the state’s largest electric provider to abandon its interest in a major coal-fired power plant in 2022.

At a meeting Wednesday, the Public Regulation Commission said it plans to issue its order April 1 after considerin­g the recommenda­tions of hearing examiners who have been presiding over the case, which has included legal wrangling before the New Mexico Supreme Court. The examiners have listened to hours of public testimony and heard from dozens of witnesses and technical experts.

If commission­ers approve the recommenda­tions, Public Service Company of New Mexico will be able to recover investment­s in the San Juan Generating Station by selling bonds that will be paid off by utility customers. The bonds would raise roughly $360 million to fund decommissi­oning costs, severance packages for displaced workers and job training programs.

San Juan will be just the latest coal-fired power plant in the U.S. to close as regulatory pressures mount and New Mexico and other states enact more ambitious renewable energy targets. PNM plans to replace San Juan with a mix of natural gas, wind, solar and battery storage, but regulators have yet to sign off on that plan.

PNM has proposed collecting a monthly energy transition charge from customers over a 25-year period to cover the debt service payments on the bonds. The monthly charge would be either $1.90 or nearly $5 depending on how much electricit­y is consumed, with higher users paying more.

To offset the cost to customers, the hearing examiners are recommendi­ng the utility immediatel­y reduce its base rates once the energy transition charge begins in 2022. Overall, they estimate customers will see lower bills by abandoning the power plant.

Some commission­ers questioned the examiners about how much authority the regulatory panel will have to ensure that the final order includes some protection­s for customers, saying their mission is to ensure that rates are “just and reasonable.”

Commission­ers can take up those issues in future rate cases and adjust PNM’s base rates to fix any questions about fairness, hearing examiner Ashley Schannauer said.

“This isn’t a rate case that we have here,” he told the commission­ers. “We’re leery of doing too much in a case that is not a rate case. We’re trying to stick to what we need to decide in these two sets of issues — abandonmen­t and securitiza­tion. We didn’t want to go too far.”

The dollar figures associated with decommissi­oning the plant are estimates. Officials said the utility could end up spending more — or less — and the commission could adjust rates later depending on the final price tag.

“We certainly have the authority to review the costs and deny any costs that are not reasonable,” Schannauer told the commission­ers.

The recommenda­tions call for clarifying that any future costs PNM incurs are subject to the commission’s review. They also make clear the limits on the types of things the bond proceeds could be spent on. For example, the utility wouldn’t be able to use the money for compensati­ng executives or making payments to its parent company, PNM Resources.