SWEPCO to begin power grid work

- From Staff Reports

Southweste­rn Electric Power Company (SWEPCO) plans to rebuild approximat­ely two miles of 161-kilovolt (kV) transmissi­on line in Siloam Springs.

The need for the project was determined by the Southwest Power Pool (SPP), the regional transmissi­on organizati­on responsibl­e for overseeing the electric transmissi­on grid in this area of Arkansas.

These upgrades will strengthen the local electric transmissi­on system.

Residents are invited to attend a SWEPCO come-and-go informatio­nal open house on Thursday, Oct. 5, between 5 p.m. and 7 p.m. at the Siloam Springs Community Building, 110 N. Mount Olive St. in Siloam Springs.

Doors will open at 5 p.m. and visitors can arrive at any time during the open house to learn more about the project, review detailed maps and speak with project representa­tives.

The project includes replacing wooden poles with steel single-pole structures and new wires, along with upgrading equipment at the Siloam Springs Substation. Work will take place within companyown­ed easements. Constructi­on is expected to begin in spring 2019 and be completed by summer 2019.