South Florida Sun-Sentinel (Sunday)

Renovating the timeline

Company seeks to reset schedule for promised school repairs after delays

- By Scott Travis

This was the year when the Broward School District promised taxpayers that repairs would be finished at 233 schools. Most are nowhere near it. With only 20 schools completed, it’s time to reset the schedule, says AECOM Technical Services, a company hired last year to take over management of the $800 million bond program,

Almost every project has been delayed, some by nearly six years from their original completion dates, under a new timeline drafted by AECOM that’s supposed to offer a more realistic timetable. Twelve schools won’t be finished until 2026, a full five years after the work was supposed to be complete, the schedule says.

“To say there have been delays would be an understate­ment,” said Adam Rabinowitz, chairman of the district’s Bond Oversight Committee.. “The public at large is dismayed.”

Parents and teachers for years have complained of mold, flooding and erratic air conditione­rs. The delays, combined with flawed estimates, have put the program nearly $500 million over budget.

The three decaying schools that were considered the poster children when the bond was pitched to voters in 2014 are still far from being finished. Constructi­on at Northeast High in Oakland Park is only 7% complete and isn’t expected to be done until late

2023. A new building planned for the school won’t be ready until

2024, according to the schedule. Blanche Ely High in Pompano Beach won’t be complete until late 2022, while Stranahan High

in Fort Lauderdale must wait until the fall of 2022. A new Stranahan cafeteria won’t happen until 2023 and could be smaller than expected, due cost overruns and declining enrollment.

It’s been a long frustratin­g wait for people at Stranahan, who were told in a 2015 community meeting that work should be complete by 2017. Constructi­on finally started in mid-2018 and has been slow and disruptive, said Thomas Harrison, the school’s athletic director.

“It’s like an a house guest who has overstayed their welcome,” Harrison said. “We want constructi­on workers off campus. We want things to get back to normal. It’s definitely taken a long time.”

More than 100 schools are still waiting for constructi­on. Among the ones facing the longest delays are Oriole Elementary in Fort Lauderdale, Sheridan Park Elementary in Hollywood and South Plantation High, which all are planned to be finished in 2026, more than 5½ years later than what was listed in a 2017 schedule.

Western High in Davie faces a similar delay, although a culinary arts lab that was part of the project was expedited and finished a year ago.

This is the second time the entire schedule has been overhauled since the district first set targeted completion dates in 2017. The first reset came in late 2018 after the district ousted then-Facilities Chief Leo Bobadilla due to problems with the bond program.

Although Superinten­dent Robert Runcie said last spring he expected the pandemic would allow the district to expedite much of the work that’s fallen behind, progress was limited, officials said.

The district was able to catch up on some roofing projects, since schools were empty for seven months in 2020, but air conditioni­ng installati­on faced slowdowns as COVID-19 led to worker shortages, Frank Girardi, executive director of capital

programs, told the Bond Oversight Committee on Monday.

“In the manufactur­ing plants, if someone on the line got sick, the whole line shut down,” Girardi said.

That delayed constructi­on of new buildings at Cypress Bay High and Falcon Cove Middle, both in Weston, he said.

Other issues blamed for delays include a dearth of qualified vendors. Many vendors have said in public meetings and interviews that they refuse to work with the district, because they often don’t often get paid on time or their plans to get stuck for months in the district’s inspection­s department. These issues are under investigat­ion

by a statewide grand jury.

Some contractor­s are turning in poor quality work but still get rehired, said Kathleen Langan, senior program director with AECOM,

“We’re experienci­ng problems with vendors and contractor­s who simply cannot seem to perform,” she said. “That has to change.”

 ?? CARLINE JEAN/SOUTH FLORIDA SUN SENTINEL ?? Student desks stand at James S. Rickards Middle School in Oakland Park on Friday. The district has released a new school-by-school timeline for when renovation work is supposed to be done, and it’s expected to take at least until 2026.
CARLINE JEAN/SOUTH FLORIDA SUN SENTINEL Student desks stand at James S. Rickards Middle School in Oakland Park on Friday. The district has released a new school-by-school timeline for when renovation work is supposed to be done, and it’s expected to take at least until 2026.
 ?? SOUTH FLORIDA SUN SENTINEL PHOTOS CARLINE JEAN/ ?? Lou D’Angelo, of West Constructi­on, walks past a newly installed fire line back flow preventer at James S. Rickards Middle School in Oakland Park on Friday.
SOUTH FLORIDA SUN SENTINEL PHOTOS CARLINE JEAN/ Lou D’Angelo, of West Constructi­on, walks past a newly installed fire line back flow preventer at James S. Rickards Middle School in Oakland Park on Friday.
 ??  ?? Constuctio­n workers work on the AC system at James S. Rickards Middle School in Oakland Park on Friday.
Constuctio­n workers work on the AC system at James S. Rickards Middle School in Oakland Park on Friday.

Newspapers in English

Newspapers from United States