Work to restart on two Urbana water and sewer projects

Projects delayed by winter weather to be completed by summer.

- By Brooke Spurlock Staff Writer

Two projects for the City of Urbana will restart on Monday after both were temporaril­y put on hold due to the winter weather.

Urbana’s Phase 2A Water and Sanitary Sewer Replacemen­t Project and Powell to Bon Air Sanitary Sewer Project will start work on Monday, according to a release from the city. Both projects were stopped in late January and early February due to the winter weather and extensive snowfall.

Both projects are slated to be complete by early summer.

Milcon Concrete, Inc., the contractor for the Powell to Bon Air Sanitary Sewer Project, has completed:

■ Installati­on of the new sanitary sewer main between the Champaign County Fairground­s and the tie-in point at the intersecti­on of Bon Air and Miller drives

■ Testing the new sanitary sewer main and place it into service after making connection to the existing sewer system

“This contractor will be completing final restoratio­n work, including final grading and seeding, driveway repair, and repaving within Oak Dale Cemetery,” the release stated.

The planned completion date for this project is May 28.

M&T Excavating LLC, the contractor for the Phase 2A Water and Sanitary Sewer Replacemen­t Project, has completed:

■ Installati­on of the new water main and services on Crescent Drive

■ Installati­on of the new sanitary sewer main and laterals on Scioto Street between Jefferson Avenue and Bon Air Drive/Berwick Drive

■ Installati­on of new water

mains and services on Finch Street and Ames Avenue

The next phase of this project will be the installati­on of replacemen­t water main and services on Scioto Street from Jefferson Avenue to Bon Air Drive/Berwick Drive.

“This phase will require temporary traffic pattern changes to allow for the maintenanc­e of traffic. With the water main installati­on planned for the north side of Scioto Street, two way traffic will be maintained on the south side of Scioto Street in a configurat­ion that will be opposite the temporary traffic control on Scioto Street that was required in 2020 for the sanitary sewer installati­on,” the release stated.

After the water main installati­on on Scioto Street, the contractor will then return to Crescent Drive to prepare this street for the replacemen­t of sidewalk, curb and drive approaches on both sides of the street as previously planned, the release stated. They will also complete final restoratio­n work on Scioto Street, Finch Street, Ames Avenue and Crescent Drive.

Scioto Street is also scheduled for complete resurfacin­g this summer under a separate ODOT Urban Resurfacin­g Program.

The planned completion date for this project is June 26.

 ?? FILE ?? Work is set to restart on two Urbana water and sewer projects after they were paused due to winter weather.
FILE Work is set to restart on two Urbana water and sewer projects after they were paused due to winter weather.