Tribe files legal challenge to stall Dakota Access pipeline
CANNON BALL, N.D. — Construction crews have resumed work on the final segment of the Dakota Access pipeline, and the developer of the long-delayed project said Thursday that the full system could be operational within three months.
Meanwhile, an American Indian tribe filed a legal challenge to block work on the pipeline, which it says poses a threat to its water supply.
The Army granted Energy Transfer Partners formal permission Wednesday to lay pipe under a North Dakota reservoir, clearing the way for completion of the 1,200-mile pipeline. Company spokeswoman Vicki Granado confirmed Thursday that construction began “immediately after receiving the easement.”
Workers had already drilled entry and exit holes for the segment, and oil had been put in the pipeline leading up to Lake Oahe in anticipation of finishing the project.
“The estimate is 60 days to complete the drill and another 23 days to fill the line to Patoka,” Granado said, referring to the shipping point in Illinois that is the pipeline’s destination.
Work was stalled for months due to opposition by the Standing Rock Sioux and Cheyenne River Sioux tribes. Both tribes argue that the pipeline threatens their water supply and cultural sites.
The Cheyenne River Sioux on Thursday asked a federal judge to stop the work while a lawsuit filed earlier by the tribes proceeds.
Energy Transfer Partners, which maintains the pipeline is safe, did not immediately respond in court to the filing. U.S. District Judge James Boasberg said he would hear arguments from attorneys Monday. The Cheyenne River Sioux told the judge that they also want to make a claim on freedom-of-religion grounds.