Sun Sentinel Palm Beach Edition

Did drilling next door damage tower?

- By Sarah Blaskey, Ben Conarck and Aaron Leibowitz

In the spring of 2016, residents of Champlain Towers South flooded complaint hotlines to fume about constructi­on activity at the neighborin­g Eighty Seven Park project that had jostled their walls, closed their pool and coated their balconies in dust.

As the complaints were spiking in mid-March, a team of consultant­s working for the developers of the luxury 18-story condo next door were just wrapping up a report on the vibrations caused by constructi­on crews driving sheet piles — a sort of subterrane­an retaining wall — into the ground directly south of Champlain Towers, at Collins Avenue and 87th Street, which divides Miami Beach from Surfside.

A report obtained by the Miami Herald showed that the vibrations exceeded the developers’ own target limits along Champlain South’s southern wall, including the span where the pool deck would cave in to the garage below five years later. The deck failed minutes before the tower collapsed on June 24, leaving 98 people dead.

The report, commission­ed by developers, was based on readings from two seismograp­hs positioned on the ground near Champlain Towers’ southernmo­st perimeter wall. Developers set a conservati­ve threshold for maximum intensity of shaking at the wall, which should have prevented even the most superficia­l cosmetic damage, according to mining industry standards. Most of the readings along the wall came in over that limit, but under levels that would do significan­t damage, according to mining industry standards.

The vibration levels recorded

at Champlain’s southern perimeter were above limits used by the Federal Transit Administra­tion to prevent damage to reinforced concrete.

Still, tremors from five years ago could not have been the ultimate cause of the June collapse, and readings along the wall were still well below levels likely to damage structural concrete, said Dr. Manoj Chopra, a geotechnic­al engineer with the University of Central Florida. There would be no reason to suspect the degree of shaking noted in the report would harm a healthy structure, he added. But the southern edge of the Champlain pool deck was not in good shape.

Overstress­ed from poor design and questionab­le constructi­on, and weakened from years of water damage and inadequate repairs, the deck was already teetering on the edge.

In 2016, Eighty Seven Park developers drove sheet piles 10 to 12 feet south of the deck, and any vibration at such close range could have worsened conditions that eventually led to the collapse, experts told the Herald.

“What vibrations would have done is aggravate the situation,” Chopra said. Under a certain amount of strain from damage, bad constructi­on and poor design, “if you shake it then definitely the vibration will have an effect,” he said.

The degree to which the drilling at Eighty Seven Park might have contribute­d to the Champlain Towers collapse has become a point of contention in litigation that has unfurled in the wake of the tragedy. The litigation casts a wide net, seeking to apportion responsibi­lity and collect compensati­on from contractor­s, consultant­s and others targeted by plaintiffs’ attorneys for actions that they say may have contribute­d to the collapse.

Eighty Seven Park is listed in a handful of the 40 or so lawsuits, a spokesman for the developmen­t team said. The developers of Eighty Seven Park maintain their project “had nothing to do with the collapse,” the spokespers­on said in a statement to the Herald.

The 2016 vibration monitoring report commission­ed by the developers concluded that, although readings exceeded the target limit set by the developers, it wasn’t enough to do structural damage to the property next door. NV5, the subcontrac­tor responsibl­e for the vibration monitoring for Eighty Seven Park, told the Herald, “the vibration monitoring results did not warrant any action.”

Photos from a 2016 visual inspection commission­ed by the developers show concrete at Champlain South was cracking prior to constructi­on commencing at Eighty Seven Park. Inspectors noted superficia­l damage along the southern wall.

Condo board documents from the time also acknowledg­ed that heavy planters along the southern pool deck had leaked water for years and caused damage to the concrete below.

The collapse also exposed damage inside the pool deck slab where it connects to the southern wall that likely wouldn’t have been visible prior to the cave-in, said Dawn Lehman, professor of structural engineerin­g at the University of Washington and consulting engineer to the Herald. Lehman, who examined photos of the collapse site, said the slab damage pattern along the southern wall was not uniform, indicating that some areas had sustained damage prior to the collapse.

“Photograph­ic evidence shows that it was damaged such that the concrete is broken into large chunks,” Lehman said. That’s different from other areas that disconnect­ed during the collapse that didn’t show “any ‘rubble like’ damage,” she said.

But there likely wasn’t just one single cause of the pre-existing damage to the slab, which was more like the cumulative result of various stressors, Lehman said. One of them could have been vibrations from constructi­on next door, she said. But the measuremen­ts in the report are “just borderline,” according to Eduardo Kausel, a retired Massachuse­tts Institute of Technology professor who specialize­s in soil dynamics. “I seriously doubt that had anything to do with the structural damage,” Kausel told the Herald.

Vibration readings were not taken at any other time during constructi­on, even when the foundation piles were driven, according to the developers.

‘I have never seen that report’

In the months leading up to the constructi­on of Eighty Seven Park, Champlain Towers South preemptive­ly hired an attorney to demand “a reasonable compensati­on package for the constructi­on and unavoidabl­e nuisances that will undeniably result from” the developmen­t project, according to his letter to developers.

In the November 2015 letter, Champlain South’s attorney Robert Zarco flagged a concern about “potential structural damage to Champlain Towers stemming from the driving of steel sheet piling into the ground.” After constructi­on crews finished driving the sheet piles and the building’s foundation, representa­tives for Champlain South followed up with a $2.4 million demand in May 2016 for cosmetic repairs and clean up, but didn’t mention any structural concerns. There’s no indication that representa­tives of Champlain South were ever made aware of the report that showed vibrations from constructi­on had exceeded the developer’s limits. “I have never seen that report,” Zarco told the Herald.

He said he was specifical­ly told to avoid structural claims. “They said we’ll handle structural at the time of the 40-year [inspection],” he said, referring to the structural review all large condo buildings in Miami-Dade undergo at that age. Champlain South was due for its 40-year recertific­ation this year.

One former condo board member, who spoke on the condition of anonymity, told the Herald that residents were complainin­g in droves about the nuisances associated with the constructi­on, and that the board was unable to do much with the complaints. Surfside town officials often deferred to the city of Miami Beach, which had permitted the constructi­on but did not come down hard on violations, the board member said.

“The key people responsibl­e for addressing the issues each had their own agenda and turned a blind eye,” the former board member said. Data from the vibration report could have quantified some of the residents’ concerns.

The March 2016 vibration report, which was prepared by GeoSonics, a subcontrac­tor of NV5, detailed 35 readings taken to measure vibration along Champlain South’s perimeter wall during the installati­on of sheet piles between March 3, 2016 and March 14, 2016. All but six exceeded a target level of 0.5 inches per second.

The 0.5 inches per second target — a measuremen­t of the movement of sediment at a given location — was based on studies by the U.S. Bureau of Mines that found consistent vibration at that level can cause cosmetic damage to plaster. A higher threshold is typically used to gauge the potential for structural damage, according to experts.

NV5, an engineerin­g company based in Hollywood, cited a figure of 3.0 inches per second in its report as the rate at which damage to “block and mortar” is possible. None of the readings along the pool deck exceeded 1.0. The Federal Transit Administra­tion standards use 0.5 inches per second as the limit for preventing damage to reinforced-concrete.

The developers maintain that the vibration report absolved Eighty Seven Park of having any impact on Champlain South with their constructi­on, and that engineers checked for indication­s of damage at the time.

“We conducted a visual inspection on the south side of the wall, which did not reveal any issues from the installati­on of the sheet piles,” said the spokespers­on, who insisted on anonymity. “By setting the benchmark at a conservati­ve .5 in/sec., the contractor was able to keep all of the vibrations below the safe levels of vibrations for residentia­l structures set by the U.S. Bureau of Mines,” the spokespers­on said. “At no time did the vibrations approach levels that would have caused structural damage to CTS.” But lawyers for the collapse victims say it’s too soon to know.

On Wednesday, attorneys for the developers turned over the report to victims’ lawyers as part of a court-ordered release of documents. Stuart Grossman, an attorney and liaison for a group of lawyers representi­ng the victims, said Thursday that a team of experts hired by the group is reviewing the report.

‘Very many complaints’

Constructi­on of Eighty Seven Park roiled Champlain South residents. In January 2016, the condo associatio­n board sent out a building-wide email with the constructi­on noise complaint hotline for Miami Beach. By March, the complaints were piling up.

“We have received the very many complaints and concerns you each have expressed to Board Members as well as the Management Office,” the board wrote to residents in an email on March 14, the final day of vibration monitoring by NV5. “These have included the recent oil on cars parked on the street level, the vibrations to the building, the dust and debris which is preventing access to balconies, the noise from the very early morning food truck with blasting music, the concern that workers begin to drill at 7 a.m. and the debris and noise caused by the auger that is drilling directly next to the pool which is preventing residents from going to the pool.”

The project stretched on for years and continued to cause ire among Champlain South residents.

In January 2019, a condo board member wrote to Surfside’s then-chief building official, Ross Prieto, complainin­g that the Eighty Seven Park project was “digging too close to our property and we have concerns regarding the structure of our building.”

The email that board member Mara Chouela sent to Prieto included two pictures of a backhoe working against Champlain South’s southern wall along the property line. Less than a half hour later, Prieto responded to Choluela’s request to stop by and check on the situation.

“There is nothing for me to check,” he wrote back. “The best course of action is to have someone monitor the fence, pool and adjacent areas for damage or hire a consultant to monitor these areas as they are the closest to the constructi­on.”

 ?? GERALD HERBERT/AP 2021 ?? In spring 2016, residents of Champlain Towers South flooded complaint hotlines to fume about constructi­on activity at the neighborin­g Eighty Seven Park project that jostled their walls and left balconies coated in dust. A report obtained by the Miami Herald showed the vibrations exceeded the developers’ own target limits along Champlain South’s southern wall.
GERALD HERBERT/AP 2021 In spring 2016, residents of Champlain Towers South flooded complaint hotlines to fume about constructi­on activity at the neighborin­g Eighty Seven Park project that jostled their walls and left balconies coated in dust. A report obtained by the Miami Herald showed the vibrations exceeded the developers’ own target limits along Champlain South’s southern wall.

Newspapers in English

Newspapers from United States