The Atlanta Journal-Constitution

Sewer problems threaten DeKalb’s growth

Aging lines can’t handle added pressure; warning letters go out.

- By Mark Niesse mark.niesse@ajc.com

Five developers interested in locating businesses in DeKalb County will have to wait, for now, because officials say aging sewer lines can’t handle the additional load.

DeKalb’s problems with sewer spills are overflowin­g into the business community, with officials finding themselves in the unusual position of holding up developmen­t in several areas of the county.

Plans to transform a vacancy in the busy Toco Hill shopping center into a sit-down restaurant, medical offices and retail stores hit an unexpected hurdle when a letter arrived from the county saying the sewer system could be a problem.

“Obviously, without sewer, we can’t build,” said Archie Wanamaker, an associate broker for Crim & Associates, which plans to complete its purchase of the LaVista Road property by the end of the year. “The hope is that we can find a resolution and have the ability to continue with our project.”

Four other developmen­ts across DeKalb recently received similar letters from the county.

The county sent sewer

evaluation letters for proposed mixed use and business developmen­ts in Brookhaven, Decatur, Doraville and Dunwoody. The Atlanta Journal-Constituti­on obtained the letters from the county through Georgia’s Open Records Act.

If the government and businesses aren’t able to quickly resolve these sewer limitation­s, potential economic growth and job creation will be delayed.

The county has been under a federal judge’s order to upgrade its sewer lines since 2010, but the infrastruc­ture improvemen­ts haven’t come quickly enough to add needed sewer capacity.

That it’s come to this “is just a colossal failure of communicat­ion,” said Chamblee Mayor Eric Clarkson at a Monday meeting with DeKalb officials. “The county should have been upgrading sewer lines a long time ago.”

It’s unclear whether the sewer issues will delay businesses from opening on schedule. DeKalb officials are meeting with businesses to try to find solutions. The county’s code currently requires that sewer upgrade costs be paid by the businesses rather than the government.

No business has been turned away. Projects can move forward if the businesses pay for improvemen­ts to the waste water collection system, officials say.

The Toco Hill property will propose installing septic tanks that would hold wastewater that could be discharged during off-peak hours, minimizing the risk of overburden­ing sewer lines, Wanamaker said. If Doraville’s economic developmen­t director approved, the tenants could move in on schedule next June.

The county also sent a letter this month about the proposed Nexus mixeduse developmen­t in Doraville, which would put apartments, a hotel, offices and retail space where a Kmart once sat. For that property, the developer could install a $50,000 lift station that would push sewage uphill to a larger basin that can handle the flow, said Luke Howe, Doraville’s economic developmen­t director.

The developer, Stephen Macauley of Macauley Investment­s, didn’t return a phone message.

“The timing is what worries me. I’m confident that we’ll work through it. But in the meantime, we’ve already got users lined up for Nexus,” Howe said.

The county government will meet with each new business that presents a problem for the county’s sewer system because of the size of the project and the sewer system’s limitation­s, said DeKalb Chief Operating Officer Zach Williams.

“It forces everyone to the table to see how we can work together to address their capacity constraint­s,” he said. “In certain areas, we have reached capacity thresholds that require us to address them in order for us to allow developmen­t to move forward.”

Though businesses and the county government may be able to find temporary fixes, permanent solutions will take time, and more businesses could receive sewer alert letters.

The county will continue to assess its sewer limitation­s, clean sediment buildup to add capacity and eventually replace infrastruc­ture as needed.

“It’s a big deal,” said Commission­er Nancy Jester. “The urgency is we have to deploy the resources necessary to regain capacity. We cannot just let people and developmen­t wither on the vine because we’re not addressing these issues very quickly.”

DeKalb has been trying to reduce sewer spills for years, and it recently acknowledg­ed under-reporting them.

The county government said it failed to report 35 out of 555 total sewer spills over the last four years. DeKalb could face fines from the U.S. Environmen­tal Protection Agency.

‘The timing is what worries me. I’m confident we’ll work through it. But in the meantime, we’ve already got users lined up for Nexus.’

Newspapers in English

Newspapers from United States