The Atlanta Journal-Constitution

Cost of I-85 bridge may reach $16.6M

Constructi­on on pace to be finished before target date of June 15.

- INTERSTATE BRIDGE COLLAPSE By David Wickert dwickert@ajc.com Bridge cost continued on A7

Rebuilding a collapsed section of I-85 in Atlanta will cost taxpayers up to $16.6 million, state officials said Tuesday.

And though Georgia Department of Transporta­tion officials have not announced a new timetable for completing the project, they say constructi­on is progressin­g at a pace that it’s likely to be done before the official June 15 completion date.

“June 15 is the latest this bridge gets completed,” GDOT constructi­on director Marc Mastronard­i said at a news conference.

Tuesday’s announceme­nts provided more clarity to a project that has obsessed hundreds of thousands of metro Atlanta commuters since one of their main highways into the city went up in flames March 30.

Basil Eleby, a homeless man, has been accused of setting the fire that caused the northbound lanes near Piedmont Road to collapse and irreparabl­y damaged the southbound lanes. Others say GDOT itself — which stored constructi­on material under the roadway that fueled the blaze — is also responsibl­e for the highway’s closure.

Mastronard­i said $16.6 million is the maximum the bridge will cost.

He said constructi­on of the new bridge will cost about $11.9 million, while demolition of the old one cost $1.6 million. The estimate also includes incentives of up to $3.1 million for contractor C.W. Matthews to complete the work before June 15.

The U.S. Department of Transporta­tion has already provided $10 million toward the cost of the project. Mastronard­i said the federal government ultimately will cover 90 percent of the cost of the bridge.

Since the fire, contractor C.W. Matthews has worked round-the-clock to demolish and rebuild 350 feet of highway in each direction. For the contractor to get the full incentive, the work would have to be done by May 15.

Mastronard­i said it’s hard to say how far in advance of June 15 the work is likely to be done.

“In terms of progress, we couldn’t be happier,” he said.

By the end of Tuesday, the contractor was expected to place all 61 beams required to support the new bridge deck. It also was prepared to set deck spans for five of the six bridge spans and install reinforced steel ties on two of the six deck spans.

Mastronard­i said he expected the company to begin pouring the deck for the first of the six spans tonight.

Meanwhile, work has begun on repaving a 6.6mile stretch of I-85 from I-75 to Clairmont Road. That $22.9 million project won’t be finished until next February.

But Mastronard­i said some of the most intensive work will be done while that stretch of I-85 is closed for the bridge constructi­on.

 ?? JOHN SPINK / JSPINK@AJC.COM ?? Crews staged bridge beams near the old toll plaza on Ga. 400 as Piedmont Road closed Tuesday morning for 24 hours for I-85 bridge repairs.
JOHN SPINK / JSPINK@AJC.COM Crews staged bridge beams near the old toll plaza on Ga. 400 as Piedmont Road closed Tuesday morning for 24 hours for I-85 bridge repairs.
 ?? JOHN SPINK / JSPINK@AJC.COM ?? By the end of Tuesday, contractor C.W. Matthews was expected to place all 61 beams required to support the new bridge deck. It also was prepared to set deck spans for five of the six bridge spans and install reinforced steel ties on two of the six deck...
JOHN SPINK / JSPINK@AJC.COM By the end of Tuesday, contractor C.W. Matthews was expected to place all 61 beams required to support the new bridge deck. It also was prepared to set deck spans for five of the six bridge spans and install reinforced steel ties on two of the six deck...

Newspapers in English

Newspapers from United States