Ga. Power’s plans for toxic coal ash ponds violate law, says group

Sierra Club plans suit; utility defends closure process for 29 sites.

- By Russell Grantham

The Sierra Club said Georgia Power’s plans to close its toxic coal ash ponds will dump heavy metal-laden wastewater into the state’s rivers and lakes and violate the federal clean water law.

Georgia Power is planning to shut down 29 ponds that hold coal ash, a waste product of burning coal that can contain toxic metals such as mercury, lead, arsenic and other toxins, according to the environmen­tal group.

Some environmen­tal groups initially praised Georgia Power’s plans. The utility expects to spend roughly $2 billion closing the sites by recycling or treating water from the ponds. The ash is to be removed and added to other ponds or landfills, recycled, or sealed in place.

But in a notice Monday of a planned lawsuit against Georgia Power, the Sierra Club said the plan will violate the Clean Water Act because existing wastewater permits for its power plants haven’t been modified to allow the utility to “dewater” the ponds by removing all of the contaminat­ed water.

Such water from the depths of the ponds is much dirtier than at the surface, the group said. The group said the wastewater goes into rivers and lakes, endangerin­g public health and wildlife.

The group said Georgia Power is also currently violating the law at a former power plant. Since December, the utility has been illegally emptying ponds at its retired Plant McManus, near Brunswick, without modified permits, the group said.

“Sampling data from every single month since dewatering began (at McManus) confirm the presence of heavy metals in these discharges, including arsenic, chromium, mercury, nickel, and selenium,” the group said.

The Sierra Club notice told Georgia Power that it will seek an injunction halting the company’s current and planned efforts to empty the ponds unless it agrees with 60 days to “fully and promptly remediate” the alleged violations.

Georgia Power spokesman Jacob Hawkins responded with an emailed statement: “Georgia Power is in full compliance with all environmen­tal regulation­s, which are enforced by the Georgia Environmen­tal Protection Division, and we will vigorously defend against any allegation to the contrary. Throughout our ash pond closure process, we are going above and beyond regulatory requiremen­ts to protect Georgia’s water quality.”

Hawkins did not respond to questions about what levels of heavy metals are in the water at Plant McManus and the other plants, or why it has not sought to modify its wastewater permits.

Environmen­tal groups, Georgia Power and state and federal regulators have been in something of a tug of war over what levels of pollutants power plants can discharge.

About three months ago, the federal Environmen­tal Protection Agency moved to delay Obama-era wastewater rules for coal-fired power plants that require them to use the most up-to-date technology to remove lead, arsenic and other toxins.

The new rule begins to take effect next year but can be delayed until 2023 in some cases.