The Atlanta Journal-Constitution

Georgia PSC wants hard numbers on Plant Vogtle project

-

State utility regulators want Georgia Power to answer several questions — including how much more it will cost — when the Atlanta utility turns in its recommenda­tion later this month on what to do with the troubled Plant Vogtle nuclear project.

Georgia Power faces an Aug. 31 deadline to file its recommenda­tion for the Vogtle expansion in the wake of the late-March bankruptcy of key contractor Westinghou­se Electric.

Options being considered include abandoning the project, completing one or both of the new reactors under constructi­on or switching to another type of power plant.

The Georgia Public Service Commission will have final say on the project’s fate.

Most of the commission’s five members have indicated they don’t want to abandon the project. But some also have said they’re worried about the project’s soaring costs and a shaky $3.7 billion financial guarantee from Westinghou­se parent Toshiba Corp., which has also been financiall­y wounded by losses on the project.

“I do want to see this project completed,” PSC Commission­er Lauren “Bubba” McDonald said Tuesday. “I do not like to see failure.”

Neverthele­ss, he cast the single “nay” in a 4-1 vote Tuesday by the PSC instructin­g Georgia Power to answer 14 questions when it turns in its recommenda­tion.

McDonald, who attended the meeting by phone, did not explain his vote.

Key questions the PSC wants answered include costs and timetables for the various Vogtle options.

The most controvers­ial question included in PSC Chairman Stan Wise’s motion was whether the commission should approve a revised constructi­on cost and schedule for the project.

Last week, the PSC’s staff opposed such a move, saying it could hamstring the agency’s ability to later challenge some of the project’s cost overruns. But a Georgia Power lawyer said then that the company could not go ahead with the project without approval of revised cost estimates.

The project to expand the plant near Augusta was already over three years behind schedule and more than $3 billion over budget when Westinghou­se filed bankruptcy.

Southern Company, Georgia Power’s parent, recently provided estimates indicating the expansion will cost more than $25 billion and will not be completed before 2023, adding more than two additional years to the schedule.

Currently, Georgia Power is spending roughly $50 million per month for its share of the project, financed by surcharges on customers’ bills. Georgia Power owns 45.7 percent of the project. Oglethorpe Power, MEAG and the City of Dalton own the rest. Oglethorpe and MEAG supply power to electric power cooperativ­es and municipal utilities, respective­ly.

Another key question in Tuesday’s motion is how a $3.7 billion guarantee to Plant Vogtle’s owners from Toshiba Corp., Westinghou­se’s parent company, will figure in Georgia Power’s analysis. Georgia Power and Vogtle’s other partners expect to start receiving payments from Toshiba starting in October.

Newspapers in English

Newspapers from United States