The Atlanta Journal-Constitution

Feds investigat­ing Plant Vogtle nuclear project’s twin in S.C.

SCANA Corp. ordered to supply documents to U.S. attorney’s office.

- By Russell Grantham rgrantham@ajc.com

SCANA Corp. says it has received a subpoena from the U.S. Attorney’s Office seeking “a broad range of documents” related to a South Carolina nuclear plant project that was shut down in late July.

The company said in a statement it would “cooperate with the government’s investigat­ion.”

The State newspaper in Columbia reported Thursday that a federal grand jury is investigat­ing SCANA’s actions in relation to the failed nuclear project.

The move comes as the Georgia Public Service Commission voted Tuesday to begin a review of Georgia Power’s recommenda­tion to continue building two new nuclear reactors at Plant Vogtle, near Augusta. The Plant Vogtle project is virtually identical to the one in South Carolina, and has been troubled by similar cost overruns and constructi­on glitches.

Georgia Power owns about half of Plant Vogtle and the half-finished reactors, which used the same designs, suppliers and contractor­s as the doomed South Carolina project.

The Vogtle expansion was more than three years behind schedule and more than $3 billion over budget when its key contractor, Westinghou­se Electric, filed bankruptcy in March due to losses on the two projects.

The two partners in the South Carolina project, SCANA Corp. and a state-owned utility, Santee Cooper, opted to abandon their unfinished $14 billion project, citing rising cost overruns, slipping electricit­y demand and expected delays and additional costs due to the Westinghou­se bankruptcy.

Last month, Georgia Power recommende­d completing constructi­on at Vogtle under the utility’s management, even though the disruption­s due to the Westinghou­se bankruptcy are expected to add more than two years of delays and more billions of dollars of cost overruns.

Its final price tag and build time are now projected to be roughly doubled, to up to nearly $28 billion and a late-2022 completion date, instead of $14 billion and 2017.

That includes about $4 billion in financing costs and tax reimbursem­ents paid through surcharges on Georgia Power customers’ electricit­y bills.

The PSC, which has final say, is expected to make a decision in February, but most of the commission’s five members have already signaled that they don’t want to abandon the project.

Newspapers in English

Newspapers from United States