The Atlanta Journal-Constitution

Georgia Power appeals for completion of Plant Vogtle

Utility, partners say they’re united in backing expansion.

- By Anastaciah Ondieki Anastaciah.Ondieki@ajc.com

Georgia Power and partner companies overseeing the constructi­on of nuclear plant, Vogtle, presented a united appeal Monday to PSC commission­ers, as hearings began on the fate of the embattled nuclear power plant.

The CEO’s led by Georgia Power’s Paul Bowers argued the project would present “the best economic choice” and “long-term benefits to customers.”

“We believe nuclear is the dominant solution. We are confident you will make the right long-term solution for the people in Georgia,” Bowers told the commission­ers.

A statement by Georgia Power said the CEO’s and their boards unanimousl­y agreed to the expansion of Vogtle 3 and 4.

The unity could be challenged by a revision in August of their contract agreement, allowing the co-owners of the project, Oglethorpe, Municipal Electric Authority of Georgia and Dalton Utilities to abandon the project if the PSC disallows costs and schedule. Under a previous agreement, co-owners could not unilateral­ly abandon the agreement.

The new agreement worries commission­ers and consumers alike, as the risk of project abandonmen­t by the co-owners could be imminent.

Following Westinghou­se’s exit due to bankruptcy the contract is now managed by Southern Nuclear, an affiliate of Georgia Power’s parent company Southern company.

Dividing issue

Plant Vogtle’s constructi­on has attracted both support and opposition within the state. Proponents and opponents of the project presented arguments before the packed commission hearing why the project, marred by cost over-runs, incessant delays and the March bankruptcy of Toshiba’s Westinghou­se, should or should not be given a go-ahead.

Debbie Dooley, of Energy Freedom USA called for the company to “add consumer protection­s and shift part of the financial burden to Southern Company shareholde­rs.” She argued placing caps on constructi­on costs on Vogtle would safeguard customers from Vogtle’s financial burden.

The commission­ers now face the task of evaluating the cost and schedule estimates presented by Georgia power, to determine the fate of the project.

“There was always some chance this commission would rule that some of the costs were unreasonab­le.” Commission chairman Chuck Eaton said.

Georgia Power and its co-owners however want to know whether these estimates are reasonable before going on.

“We need to know before we spend additional dollars,” said Bowers.

In March, plant Vogtle’s lead contractor Westinghou­se Electric- owned by Tokyo based Toshiba Corp., filed for bankruptcy citing financial losses. The project was already three years behind schedule and more than $3 billion over budget.

Westinghou­se’s bankruptcy resulted in the shutdown of a $14 billion project in neighborin­g South Carolina in August, with partners citing increasing risks, incessant delays and cost overruns. Westinghou­se was also the lead contractor in the project.

Expansion of the project, to include two additional nuclear reactors at Plant Vogtle which began in 2009 has been hampered by falling natural gas prices and competitio­n from alternativ­es such as solar and wind power.

The project has been marred with numerous delays and cost overruns, with Southern company, which owns Georgia Power, saying project completion date, initially set for 2017, would run past 2023.

Georgia Power owns 45.7 percent of the project and currently spends $50 million per month of its share on the project, with its customers financing the project through surcharges on their bills. Other co-owners of the project include Oglethorpe Power (30%), Municipal Electric Authority of Georgia (22.7%) and Dalton Utilities (1.6%).

In August, a $14 billion nuclear project in South Carolina overseen by Westinghou­se was shut down, with major stakeholde­rs citing the company’s bankruptcy, skyrocketi­ng costs, project delays and the falling demand for energy.

Plant Vogtle is one of the two nuclear power plants in Georgia. It’s the only new nuclear power plant to be built in the U.S. in 30 years.

Newspapers in English

Newspapers from United States