The Atlanta Journal-Constitution

PSC analysts: Scrap Vogtle project

Nuclear power venture has been beset by cost overruns, delays; backers tout job, energy benefits.

- By Anastaciah Ondieki Anastaciah.Ondieki@ajc.com

Analysts appointed by the Georgia Public Service Commission to evaluate progress at Plant Vogtle in Augusta say the project should be canceled as Georgia Power failed to manage it in a “reasonable manner.”

“Completion of the project is no longer economic given the additional costs and schedule delays,” the analysts said in written testimony to commission­ers.

They recommende­d that a reasonable total project cost be set at $8.3 billion, $3.9 billion less than what Georgia Power estimates for project completion.

The experts opposed Georgia Power and partner company requests to shift the projects financial risks resulting from contractor’s failures to customers as some costs “incurred by the company were not reasonable to allocate to customers.” Instead, they said Georgia Power and its shareholde­rs should shoulder the risk.

The company has not provided justificat­ion in its requests to apportion ratepayers 100 percent of its forecasted costs, the analysts said.

Georgia Power through spokespers­on John Kraft argued the company shared in the “financial risk of the Vogtle project,” citing “severe consequenc­es for delays in place

under an agreement with the Georgia PSC.”

The analysis, based on Georgia Power reports presented during the November commission hearings, also showed the company was not “effective on a consistent basis in assuring that all the key project commitment­s were being met by the Contractor on a timely basis.”

The test i mony comes weeks after Georgia Power CEO Paul Bowers’ assertion before commission­ers that completing the project presented the best economic option for customers. CEOs of companies partnering with Georga Power — Oglethorpe Power, Municipal Elec- tric Authority of Georgia (MEAG) and Dalton utilities — appealed to commission­ers to approve the new proj- ect costs and have customers continue funding the project.

In November, Bowers asked commission­ers to rule on whether the new estimates by Georgia Power and its partners were reasonable, before the company, which owns 45.7 percent of Vogtle, continues spending additional dollars on the project.

As of June, total project Ccosts incurred on the project stood at $5.85 billion. Georgia Power estimates total proj- ect costs at completion to be $12.2 billion, with completion dates for units 3 and 4 set for November 2021 and 2022 respective­ly. No plan for nine years inghouse Former Electric contractor Company, West- had “struggled to keep the design” at pace with con- struction, resulting in frequent design changes and subsequent project delays.

“By March of 2018 the Company and Consortium (Westinghou­se) would have worked without an Integrated Project Schedule for 9 years,” the analysts found.

A lack of a project sched- ule affected the schedule and costs.

Based on the latest analy- sis, additional delays “would have a significan­t adverse impact on the economics of the 2012 Project project.” raised monitors concerns have since that costs and schedule projection­s provided by Westing- house were “severely under- estimated” due to a lack of a fully Integrated Project Sched- ule (IPS).

In his testimony in May, 2012 independen­t monitor William Jacobs said the status of the project was at the time “unclear” as an agreed upon schedule did not exist.

The monitors argued that had a proper analysis been done, a more accurate pic- ture of the project’s value would have been developed before hundreds of millions of dollars of sunk costs were incurred.

Awaiting the PSC decision

The question of whether to proceed with construc- tion of the two reactors in Augusta continues to be a divisive issue, and the fate of the project is dependent on a decision in February by the commission­ers. The analysts said failure by the commission to adopt their recommenda­tions and grant Georgia Power’s requests could “preclude the ability” of a future commission to disallow unreasonab­le costs. Groups supportive of the project argue the plant will create skilled employment, boost the local economy and provide energy alternativ­es. Mary Korsnick of t he Nuclear Energy Institute, which supports nuclear energy and technology, said the plant would help main- tain an energy mix besides ensuring “safe, reliable, clean air electricit­y.” Brent Booker of North America’s Building Trades Union sees Vogtle as an opportunit­y to provide a new crop of highly skilled craft workers in the nuclear field, skills he says are “unique” to the industry. Southern Peter Bradford Alliance for of Clean the Energy called on commission­ers to disallow Georgia Power’s new cost estimates as its past forecasts have been “devastatin­gly wrong to date.” He also called on commission­ers to disapprove the new management structure. The project, marred by cost overruns and schedule delays, is now managed by Nuclear Southern, a subsidiary of Georgia Power’s parent company Southern Company, which took over after the March bankruptcy by Westinghou­se Electric Company. In August, Bechtel took over constructi­on at the site from Flour Corporatio­n.

Economic prospects for completing Vogtle are diminishin­g in light of natural gas estimates, which indicate a decrease in natural gas prices. The analysts found Georgia Power’s previous natural gas price estimates “overstated” as they were not indicative of the “accurate view of market consensus.”

Falling demand for nuclear, rising costs, constructi­on delays and Westinghou­se’s bankruptcy led to the decision in July for Scana and Santee Cooper to pull the plug on the V.C Summer project in South Carolina. The VC Summer project employed the same technology being used on the Vogtle plant and was estimated to cost $14 billion.

Vogtle has been rife with “low productivi­ty,” with reports of “idle time, early quits and late starts remained high,” among workers on the plant. A report in June showed progress had “slipped” and “constructi­on had “not met the completion rate needed to support the project schedule.”

According to Bowers, once complete, the plant, the first to be built from scratch in the United States in 30 years will contribute 21 or 22 percent of Georgia’s electricit­y. Currently nuclear power contribute­s 19 to 20 percent of electricit­y in the state.

 ?? BRANT SANDERLIN / BSANDERLIN@AJC.COM ?? The Plant Vogtle project, marred by cost overruns and schedule delays, is now managed by Nuclear Southern, a subsidiary of Georgia Power’s parent company Southern Company, which took over after the March bankruptcy by Westinghou­se Electric Company.
BRANT SANDERLIN / BSANDERLIN@AJC.COM The Plant Vogtle project, marred by cost overruns and schedule delays, is now managed by Nuclear Southern, a subsidiary of Georgia Power’s parent company Southern Company, which took over after the March bankruptcy by Westinghou­se Electric Company.

Newspapers in English

Newspapers from United States