Power lines may help quell clashes in Kashmir region

Leader seeks warm homes, hearts in violence-torn state.

- By Saket Sundria and Rajesh Kumar Singh

In Prime Minister Narendra Modi’s push to supply electricit­y to every Indian household, connecting homes in the state of Jammu & Kashmir might be the toughest.

Along India’s violence-prone northern border, engineers and constructi­on workers are hauling tons of high-tension wires and steel frames on pack mules across barren desserts and mountain ravines to electrify one of the country’s most inhospitab­le states. Still, the effort, budgeted to cost 48 billion rupees ($740 million), may turn out to be Modi’s most rewarding.

In some villages, winter outages persist for 20 hours a day even as temperatur­es dip to minus 35 degrees Celsius (minus 31 degrees Fahrenheit). Modi is counting on 24-7 power to warm both homes and hearts in the Muslim-majority state, where as many as 70,000 terrorists, security forces and civilians have died in independen­ce-fueled clashes in the past three decades. Constructi­on of key infrastruc­ture in the Kashmir Valley may be helping.

“People understand the value of this project since very few large developmen­t projects are happening in the valley,” said Pratik Agarwal, chief executive officer of Sterlite Power Transmissi­on, which is building the state’s first private transmissi­on line. “We have been getting incredible support as power is something people can relate to — it’s something that everyone wants.”

When the first equipment reached a spot about 40 kilometers (25 miles) from Srinagar, one of the state’s two capital cities, in May 2016, locals protested what they thought was the makings of an army camp. As an electrical substation emerged, opposition gave way. Now, two neighborin­g villages are squabbling over rights to get their name on it.

The enthusiasm reflects an eagerness for electricit­y in a state lacking a fifth of the peak energy it needs. It also points to infrastruc­ture as a potential avenue for Modi’s Bharatiya Janata Party to garner greater support from Muslim Kashmiris, some of whom have violently opposed the controllin­g force of New Delhi, 825 kilometers south of Srinagar.

Electricit­y shortages have long been a bane in the Kashmir Valley, and providing reliable, affordable, constant power could go some way in quelling unrest, according to Noor Ahmad Baba, dean of the school of social sciences at the Central University of Kashmir.

Baba traces a connection between lack of electricit­y and militancy, drawing from his observatio­ns as a youth in the late 1980s, when insurgency escalated in Kashmir.

“Poor electricit­y supplies not only deprive Kashmiris of education, employment and medical facilities, but also very basic things like entertainm­ent and communicat­ion,” he said over the phone from Srinagar. “This leads to a lot of discontent.”

While the state’s capitals, Srinagar and Jammu, have electricit­y most of the day, towns and villages like Haft Chinar, on the outskirts of Srinagar, don’t. “We barely get power now — three-to-four hours a day at best,” said Tanveer Hussain, 40, who helps guard a newly built substation that he sees improving lives. “This has helped a lot of us. We got jobs and hope to get power, too, so my children can study and have a better life.”

The lack of power is an economic drain on the state, according to Fayaz Ahmad Punjabi, junior vice president of the Kashmir Chamber of Commerce and Industry. “Electricit­y is like food for industry, it’s a necessity,” he said. “But in Kashmir today, it’s a luxury. So industry suffers, people suffer. Power is life, and we don’t have enough of it.”

Modi pledged to bring power to 18,452 non-electrifie­d villages within 1,000 days in his August 2015 Independen­ce Day national address. As of Oct. 31, electricit­y had reached 15,218 or 82 percent of those villages. In Jammu and Kashmir, 100 out of 134 villages, encompassi­ng 270,000 households, lacking electricit­y were still waiting to be connected.

The government is trying to speed up progress with transmissi­on-line projects.

The Sterlite project will bring power from Jalandhar, in northern Punjab state, to Amargarh, near Srinagar, along a 441-kilometer line running parallel to the so-called Line of Control that marks part of India’s de facto northern border with Pakistan.

The project, which will cost more than 26 billion rupees, is almost finished and Sterlite aims to start supplying as much as 1,000 megawatts to the power-starved valley in late December, several months ahead of schedule.

A dearth of suitable roads in some remote areas meant dozens of mules were used to haul constructi­on material and Sterlite hired an air crane from Erickson Inc. to lift pieces for transmissi­on towers to peaks as high as 3.8 kilometer (12,500 feet) in the Pir Panjal Range.

“We got incredible support from the state government,” said Agarwal, Sterlite’s CEO. “We’ve been working relentless­ly despite the curfews, despite the unrest”

A second project managed by state-owned Power Grid Corp. will run electricit­y 350 kilometers from Srinagar to the Ladakh region in the state’s northeast, bordering China.

“Kashmir and Ladakh freeze in winter,” said Nirmal Kumar Singh, Jammu & Kashmir’s deputy chief minister, in an interview. “Transmissi­on is a big hurdle.”

The state’s peak power demand is about 2,700 megawatts, though it gets merely 2,100 megawatts — about 1,100 megawatts from hydro electricit­y produced within the state and the rest from other states through an existing transmissi­on line. A lack of transmissi­on capacity prevents it bringing in more.

Ladakh, a desert region with about 300,000 people between the Himalayan and Karakoram mountains, gets only about 25 megawatts of hydroelect­ricity in summer. In winter, it plunges into darkness, save a couple of hours each day when army-supplied, diesel-powered generators run.

Power Grid’s line will cost 22 billion rupees and carry as much as 150 megawatts of electricit­y over mountains 4.6 kilometers above sea level when it’s completed in 2018.

 ?? PRASHANTH VISHWANATH­AN / BLOOMBERG ?? Power lines crisscross Leh Bazar, in the state of Jammu and Kashmir, India. The effort to provide sufficient electricit­y in the northern border state is estimated to cost $740 million.
PRASHANTH VISHWANATH­AN / BLOOMBERG Power lines crisscross Leh Bazar, in the state of Jammu and Kashmir, India. The effort to provide sufficient electricit­y in the northern border state is estimated to cost $740 million.