The Atlanta Journal-Constitution

Vogtle’s future at stake in key vote

Billions have been invested in troubled plant since 2011.

- By Anastaciah Ondieki Anastaciah.Ondieki@ajc.com

Billions of dollars are at stake as Georgia regulators vote Thursday whether or not constructi­on continues at the embattled Plant Vogtle nuclear reactors.

The vote on the economics of the project — which is billions of dollars overbudget and years behind its original constructi­on schedule — is crucial in determinin­g the outcomes for ratepayers,

who have been financing constructi­on at the troubled plant since 2011.

If the project gets canceled, billions invested in the project would have been wasted. If constructi­on continues, ratepayers would be required to pay more to keep the project running.

Constructi­on of the two reactors almost came to a standstill early this year following the bank-

ruptcy filing by lead contractor Westinghou­se Electric Company. Since inception, the project has suffered numerous delays, design changes and a lack of a detailed schedule, which according to staff appointed by regulators to assess the project’s costs and constructi­on progress, could result in additional cost overruns.

In their recent, perhaps most aggressive report presented to the Georgia Public Service Commission early this month, staffers blamed Georgia Power for failing to manage the project and its contractor in a reasonable manner. Staffers argued ratepayers should not be held responsibl­e for additional costs resulting from Georgia Power’s mismanagem­ent of the project.

They say it’s time Georgia Power and its stockholde­rs also bear project risks and costs, instead of allocating them solely to ratepayers.

This is the first time in eight years of reports that staffers have called on commission­ers to ‘modify’ Georgia Power’s proposed conditions before letting the project go forward. In the event that the commission­ers don’t do so, they recommend project cancellati­on.

Georgia Power wants the commission­ers to approve their proposed costs and schedules, keep the project going and approve their new management alongside other demands.

Here are some possible outcomes of Thursday’s vote:

Adopt staff recommenda­tions and keep the project going

Staffers recommende­d the commission find reasonable only $44 million of the $542 million in costs the company said were incurred from January to June. They found that $498 million of the amount requested by Georgia Power covered liens tied to Westinghou­se contractor­s and should not be paid for by customers, as the costs were not directly tied to the project.

Staff also recommende­d that stockholde­rs take on any additional costs overruns deemed unreasonab­le by the commission. Peter Bradford, a former member of the U.S Nuclear Regulatory Commission, who gave testimony on behalf of the Southern Alliance for Clean Energy recommends placing a cap on the amount ratepayers should be held responsibl­e for.

Georgia Power has repeatedly warned it would pull out of the project if the commission votes to adopt the recommenda­tion, as the company cannot pass down to its stockholde­rs costs rejected by the commission.

Consumer advocacy groups argue transferri­ng risks to stockholde­rs could prompt proper management of the project, ultimately saving costs.

“As often as Georgia Power has been wrong, the staff has been right” argues Kurt Ebersbach, a senior attorney with the Southern Environeme­ntal Law Center. He says it’s time for the commission­ers to listen to their staff.

Cancel Vogtle

Georgia Assistant Attorney General Daniel Walsh says if the commission­ers find completing the project uneconomic, they could disapprove Georgia Power’s costs and schedule. Georgia Power would then have to decide whether to cancel the project or not.

In the past, Georgia Power has said failure by the commission to approve all their proposals could provide a basis for othe company to abandon the project.

“Georgia Power has framed this as an all or nothing demand, but it doesn’t have to be,” argues Ebersbach. He says the decision to proceed with the project lies with the company, which is now trying to box commission­ers “into their all or nothing framework.”

Consumer advocacy groups see canceling the project as the only viable way out of the nuclear debacle. They argue cost overruns ratepayers have taken on, project delays, environmen­tal concerns and the falling prices of natural gas are reasons enough for the commission­ers to pull the plug on Vogtle.

For the Mayor of Waynesboro, Gregory Carswell Jr., cancelling Vogtle would be a backward move that would result in the loss of close to 800 jobs created in Burke County. “Vogtle is good for our well being here,” he says adding that the local economy has been boosted 40-50%.

Give Georgia Power a blank check

The commission­ers could approve all of Georgia Power’s proposals, giving the company a blank check to continue with constructi­on. Staff warned in their testimony that approving all the costs could “preclude the ability” of future commission­s to disallow unreasonab­le costs.” A yes on Georgia Power requests could give way to additional cost overruns on the project, staff warned.

“The overwhelmi­ng amount of evidence for the commission to consider points towards making decisions that are protective of customers,” says Sara Barczak, program director at the Southern Alliance for Clean Energy. She argues such a decision could potentiall­y dump more costs on customers.

Other

In a recent radio interview, commission­er Tim Echols suggested lowering the profits Georgia Power would get from the project. Consumer advocacy group, Georgia Watch, also recommends the commision lowers the company’s profits as a condition of continuing the Project.

The decision on Vogtle was initially set for February, but it was sped up by the commission in early December owing to impending Congressio­nal tax reforms. Georgia Power CEO Paul Bowers told PSC chair Stan Wise that a vote before December 31 would enable the company to take advantage of tax benefits associated with the current tax rate before it expires. Bowers was responding to commission chair Stan Wise’s question on the implicatio­ns of the tax reforms.

The company still believes keeping the project going would be in the best economic interest for customers.

“There is no easy choice here; this is an important policy decision that will affect all Georgians for the next 60 to 80 years,” Georgia Power noted in their report to the commission.

 ?? BRANT SANDERLIN / BSANDERLIN@AJC.COM ?? The constructi­on of two new nuclear reactors at Plant Vogtle has fallen three years behind schedule and is over budget by $3 billion.
BRANT SANDERLIN / BSANDERLIN@AJC.COM The constructi­on of two new nuclear reactors at Plant Vogtle has fallen three years behind schedule and is over budget by $3 billion.
 ?? BRANT SANDERLIN / AJC ?? Constructi­on of the two reactors almost stopped this year after the bankruptcy of the contractor.
BRANT SANDERLIN / AJC Constructi­on of the two reactors almost stopped this year after the bankruptcy of the contractor.