Intersecti­on to close for two weeks to finish roundabout

- By Mitchell Northam Mitchell.Northam@ajc.com

The city of Roswell announced last week that it will close the intersecti­on of Hardscrabb­le and Chaffin roads for two weeks to shorten the constructi­on time of the Hardscrabb­le Green Loop Project.

When the intersecti­on reopens, it will look a lot different. Crews will be building a roundabout there.

The closure will begin on July 9 and the intersecti­on is projected to reopen on July 23. The city estimates that this closure will shave “four to five months” off constructi­on time for the Hardscrabb­le Green Loop Project.

Through traffic will be required to detour around the intersecti­on during the two-week closure, local residents will still be allowed access. Signage will alert drivers of detours.

The entire Hardscrabb­le Green Loop project is slated to be finished by summer 2019, the city said in a recent news release. But in January, Roswell Mayor Lori Henry was optimistic about it being completed this year.

Ground broke on the project in October 2017. Design for the $5.8 million project began in 2011.

The Hardscrabb­le Green Loop will be a “complete street,” featuring intersecti­on improvemen­ts, sidewalks, bike lanes and a multiuse trail. It will allow bicyclists and pedestrian­s to use both sides of Hardscrabb­le Road. The project will add 1.2 miles of multiuse paths, 1.4 miles of sidewalk and 2.4 miles of new bike lanes.