The Atlanta Journal-Constitution

MEAG sues as Fla. utility seeks to void Vogtle deal

- By Anastaciah Ondieki Anastaciah.Ondieki@ajc.com

Rising constructi­on costs related to the expansion of nuclear Plant Vogtle have led to frayed relations between two key players who filed competing federal lawsuits this week that further threaten the future of the $27 billion project.

Municipal Electric Authority of Georgia (MEAG), a co-owner of the South Georgia nuclear plant, sits on one side of the dispute while the Jacksonvil­le Electric Authority ( JEA) is on the other. MEAG in its federal lawsuit filed Tuesday claims JEA, the Florida-based company, is trying to renege on a 2008 agreement to purchase power from the Georgia-based operator.

The agreement called for the Jacksonvil­le company to cover 41 percent of MEAG’s share of constructi­on costs at the Vogtle expansion for 20 years in exchange for power to service its residentia­l customers in Florida and Georgia.

MEAG claimed in the suit filed in the Northern District of Georgia in Atlanta that the Florida entity was “underminin­g the process by claiming that it does not have to abide by its contractua­l agreement.” The lawsuit says JEA became “irreversib­ly obligated” when the company entered into the agreement to purchase power once Vogtle Units 3 and 4 open for commercial operation. The power purchase agreement obligates JEA to pay its share regardless of “whether or not the project is completed or is operating or operable,” the lawsuit claims.

MEAG says the Florida company’s actions are premature and will damage the project in Burke County as well as MEAG’s ability to meet its obligation­s and secure financing.

“This was not an action we wanted to take, but we filed this lawsuit to protect the interests of the participan­t communitie­s that we serve,” said MEAG Power President and CEO, Jim Fuller.

The legal dispute is the latest complicati­on for a project that sits at a crossroads in the face of significan­t delays and cost overruns. When the expansion launched in 2009, the power units were scheduled to be operating by 2016. But the comple- tion date has been set back with a current target completion of November 2022.

Costs have nearly doubled over the past nine years, earning outrage from con- sumer advocates who claim gross mismanagem­ent that will ultimately cost rate- payers on their power bills. Last month, Georgia Power announced an additional cost overrun of $2.3 billion. That concerned JEA executives and set off demands for MEAG to pull out of its ownership obligation of the project.

A complex ownership structure involving four co-owners that are expected to decide in a Sept. 24 vote whether to cease constructi­on because of theproblem­s. The group includes Georgia Power (45.7%), Oglethorpe Power Corp. (30%), MEAG (22.7%) and Dalton Utilities (1.6%).

MEAG said it is “evaluating it’s decision” on the nuclear project ahead of the vote. A 90 percent vote against the project could result in Vogtle’s cancellati­on. Georgia Power, which has the largest stake, has not wavered in its support of the project.

In its effort to get out of the contract, JEA filed its own lawsuit on Tuesday in Flor- ida seeking to have the con- tract voided. The thrust of its legal argument is that the community-owned power authority did not have the right to enter the contract 10 years ago because it was not approved by the Jack- sonville City Council. Under Florida law, their argument says, the council needed to sign-off on the debt.

“There appears to be no end in sight to the ever-increasing cost and delays plaguing the constructi­on of the additional units,” JEA said in the complaint.

MEAG however argued in its lawsuit that the contract did not need city council approval as it was not considered debt, but an expense the Florida entity was obligated to pay.

Daniel Aschenbach, a lead analyst at Moody’s Investor Services said the unfolding legal challenges threaten the health of the project’s bonds which bond holders thought were stable because they viewed the agreement as valid and binding.

If JEA defaults from its portion of the contract, Aschenbach said, neither MEAG nor its 49 participat­ing communitie­s in Georgia that use its power would be required to take on JEA’s obligation.

“It is not clear how they would work it out other than it would be a quandary at that point of how to replace that part of the financing,” Aschenbach said. “If the suit has some judicial merit, that would be a credit negative for the bonds.”

Newspapers in English

Newspapers from United States