The Atlanta Journal-Constitution
DON’T ALLOW BILL QUESTIONS TO ESCALATE
Q:
We hired a local company to help us with a project on our property. After the work was done, we received a bill for more than what was agreed. The bill also included work that was not performed. Do we need to pay it? — Karl
A:
Whenever you hire someone to perform work on your home, you should have a written contract. The agreement should detail the work, its cost and when it will be complete. This will help avoid problems later by making sure everyone’s expectations are clear. I hope that you did this for your project. If so, double-check your contract to see if it matches the bill, and make sure the mistake is not on your part.
Whether you have a written agreement or not, your first step is to pick up the phone and have a direct but polite conversation with the company. I have seen many cases where the problem began with a simple misunderstanding or billing error and turned into a nightmare because neither party bothered to try to communicate with the other.
More than one contractor client has told me that he would have taken care of the issue at his cost if his customer had not immediately accused him of being a crook. Polite, but firm, conversations can solve problems.
If this does not solve the dispute, you should pay the parts of the invoice that you agree with, and send a letter describing which charges you are disputing. In my experience, most people will pay nothing when they get a bill with a small mistake. This causes a minor issue to spiral into a much larger problem.
I know of one case where a homeowner lost her house to foreclosure because she refused to pay her association anything until they cleared up a $10 error.
When disputing the charges you do not agree with, document all communication. This will help your lawyer defend your case.