The Atlanta Journal-Constitution

Chattanoog­a claims Ga. sewer utility owes $25M, seeks cutoff

Dispute over alleged unpaid bills and fines now in court.

-

A Sept. 16 letter from a Chattanoog­a city attorney says the authority owes $1.9 million in unpaid bills, as well as more than $23 million for breaching the contract.

FLINTSTONE, GA. — A Tennessee city claims that a north Georgia sewer authority owes more than $25 million in unpaid bills and fines, and wants to cut off sewer treatment for the county, but the authority says the amount owed is less than $300,000.

The chattanoog­a times free Press reports that the city of Chattanoog­a claims the Walker County Water and Sewerage Authority didn’t pay the full amount of 22 bills from October 2017 through July 2019.

The Walker County utility pipes some sewage that it collects to Chattanoog­a for treatment, paying for the service.

A Sept. 16 letter from a Chattanoog­a city attorney says the authority owes $1.9 million in unpaid bills, as well as more than $23 million for breaching the contract between the two entities.

“Walker County’s refusal to timely pay the full amounts owed is a material breach of the parties’ agreement,” wrote Phil Noblett, a deputy city attorney, demanding payment within 60 days. “That amount continues to accrue at the rate of $1,000 per violation per day,” he wrote, plus interest.

The 60 days ended Nov. 15 and the authority had not paid by then.

On Nov. 19, the sewer authority’s attorneys filed a legal response challengin­g a number of actions and charges by Chattanoog­a over the years and saying the sewer authority is, in fact, owed $279,500.

On Dec. 13, Chattanoog­a responded by filing a motion to dismiss the countercla­ims.

Earlier this year, the Walker County Board of Commission­ers voted to spend $5 million in federal COVID-19 relief funds for a water and sewer improvemen­t plan with the goal of redirectin­g sewage from the north end of the county to the sewer treatment plant in Chickamaug­a, Georgia, rather than Chattanoog­a. When asked during the September deposition if this would allow the Walker County Water and Sewerage Authority to disconnect from Chattanoog­a’s system and treat all of its own wastewater, the representa­tive for the authority said doing so would likely require another “redirectio­n project” as well as facility treatment upgrades.

In court documents, attorneys for Chattanoog­a said the city was entitled to terminate service under the 2016 agreement.

“Nothing is stopping Walker County from raising its wastewater rates to construct a treatment facility with sufficient capacity to treat all of its own wastewater,” the city argued. “Walker County can also find someone else to contract with to treat its sewage. But what it cannot do is stubbornly refuse to pay its bills, tell Chattanoog­a how it must finance capital projects necessary to treat its wastewater, and then play the victim when Chattanoog­a sues to enforce its contractua­l rights.”

Chattanoog­a’s attorneys argue that Walker County withheld payments when Chattanoog­a needed the money to comply with federal agreements to clean up its wastewater treatment system.

Attorneys for Chattanoog­a asked the court to require the sewer agency to begin taking steps to disconnect, although they acknowledg­ed that might take time.

Representa­tives of both sides declined to comment.

Newspapers in English

Newspapers from United States