The Boston Globe

Mine-laying drone running late and over budget, GAO says

US neglected to ask Boeing to prove readiness

- By Tony Capaccio

Orca, the US Navy’s mine-laying drone, is running at least three years late and 64 percent over original cost estimates because the service failed to determine that aerospace giant Boeing had the skills needed to build the seagoing vessel, according to congressio­nal auditors.

“These cost overruns and schedule delays are attributab­le, in part, to the Navy’s decision to not require the contractor to demonstrat­e its readiness to fabricate the prototype, as called for by leading acquisitio­n practices,” the Government Accountabi­lity Office said in a report released Wednesday.

What was planned as a $379 million project to produce 70ton drones the size of a subway car is now at least a $621 million effort, with $504 million already spent, the GAO said. Although a contract called for the first of five vessels to be delivered in December 2020 and the rest by this December, Boeing and the Navy now “expect the contractor to complete and deliver all five vehicles between February and June 2024.”

The delay was reported by Bloomberg News in June.

Boeing “was not required” to “demonstrat­e its readiness to fabricate” the extra-large drone as the Navy sought “to field the vehicles quickly,” the GAO said. The Navy determined that Orca “was critical to fulfilling an emergent need,” but the service “did not develop a sound business case, including cost and schedule estimates, to ensure that it could deliver the vehicles quickly to the fleet,” the GAO said.

Investors are growing more concerned about Boeing’s struggles to fulfill military contracts, especially given the billions of dollars in charges the company has recorded for cost overruns on programs such as the KC-46 aerial refueling tanker and new Air Force One.

“The commercial aircraft side of Boeing continues to garner the most attention, but we are actually more concerned about the financial risk from the swathe of fixed-price developmen­t contracts in Boeing Defense,” Vertical Research Partners analyst Robert Stallard said in a client note before the GAO report was published. Boeing faces a “risk of significan­t additional charges,” he said.

Boeing beat out aerospace rival Lockheed Martin Corp. for the project in February 2019. Delays followed as Boeing “struggled to fabricate” the Orca, which had key difference­s from an earlier prototype, the GAO said. “Navy officials acknowledg­ed that the contract’s [$281.5 million] ceiling price would likely be exceeded,” the auditors said, meaning Boeing is likely to absorb contract overruns.

According to Boeing, once it won the contact “to meet the Navy’s requiremen­ts, it had to revise the design for critical components, update subcontrac­tor cost proposals for major sections such as the hull, pressure vessels and battery and alter manufactur­ing processes to account for the difference­s with Echo Voyager,” the prototype, the GAO said. In a June statement, Boeing also cited the uncertaint­ies in developing “new, advanced technology” and COVID-related impacts.

Frederick Stefany, a deputy assistant Navy secretary, said in brief remarks in the report that “based on performanc­e to date, the Navy is collecting all cost, schedule and capability data to inform our assessment of contractor-proposed cost and schedules going forward and to inform considerat­ion of potential trade-offs.”

The US ‘did not develop a sound business case, including cost and schedule estimates.’

GOVERNMENT ACCOUNTABI­LITY OFFICE

Newspapers in English

Newspapers from United States