The Columbus Dispatch

From down under

As constructi­on continues on the I-270 interchang­e at Rt. 23, we take a trip beneath the surface

- By Rick Rouan THE COLUMBUS DISPATCH

Drivers on Rt. 23 near the I-270 interchang­e are used to seeing two things: brake lights and orange barrels.

What’s tougher to grasp from the driver’s seat, though, is the progress happening beneath the surface. In some places, that’s 30 feet below ground.

Since May, constructi­on crews have been digging out a channel that will carry northbound express lanes for about a mile, from I-270 to north of Flint Road on the Far North Side.

Excavation is about 70 percent finished, and the constructi­on team is anchoring walls and building bridges over what will be Ohio’s first traffic trench.

See

Page

The Dispatch was given a behind-the-barriers tour of the trench on Friday.

The Ohio Department of Transporta­tion is digging the trench, which will accommodat­e two northbound express lanes. Two other northbound lanes and four southbound lanes will be maintained at ground level.

As part of the same project to alleviate congestion, a stretch of Rt. 23 north of the trench is being widened, and the I-270/Rt. 23 interchang­e is being rebuilt.

It all adds up to $80 million and three years of work.

“It’s a tight corridor,” said Greg Channel, ODOT’s project engineer. “We have very little right of way to work with.”

The trench has reached its 30-foot maximum depth at both ends, but the middle still needs to be excavated. For workers in the deeper recesses, cars whiz by overhead, but only their tops are visible over the barriers that keep drivers from seeing below.

Crews will continue digging through the winter, Channel said. The trench should be open to traffic at the end of August — more than a year before the rest of the project is done.

Drivers who opt to take the trench won’t have to stop at traffic lights, which should ease some of the traffic that builds up, Channel said.

While a bridge could have had the same result, ODOT chose a trench that wouldn’t change the view and character of the area, he said.

“Initially it’s a larger investment, but in the long run, it’s more efficient” and will require less maintenanc­e, ODOT spokeswoma­n Nancy Burton said.

The trench is 36 feet wide, with a 10-foot shoulder on the right and a 4-foot shoulder on the left. It can accommodat­e city snowplows. Concrete walls that are a foot thick will be reinforced with steel. Fire hydrants will be flush with the surface of the trench.

Water that flows into the trench will be channeled into catch basins and a 24-inch drainage pipe. During constructi­on, crews have had to dig sump holes and pump water out of the trench, Channel said.

By taking the trench, drivers will avoid three local intersecti­ons: Dimension Drive, Campus View Boulevard and Flint Road. Campus View and Flint both have traffic lights.

Bridges at Campus View and Flint will carry cars over the trench. Crews are finishing the first half of the Campus View bridge and eventually will shift traffic onto the new deck to start work on the second half.

The widening of Rt. 23 north of the trench will be finished and new lanes open by the end of the year, Channel said.

New ramps at the interchang­e have opened, and a third of the Rt. 23 bridge over I-270 has been demolished. Once that third is rebuilt, ODOT will remove and rebuild the rest of the bridge.

The whole project should be finished in the fall of 2016.

 ?? DISPATCH ?? TOM DODGE
Workers in the trench on the north side of the Rt. 23/I-270 interchang­e can see only the tops of vehicles whizzing past.
DISPATCH TOM DODGE Workers in the trench on the north side of the Rt. 23/I-270 interchang­e can see only the tops of vehicles whizzing past.
 ?? DISPATCH ?? TOM DODGE Walls are going up inside the trench as it’s being dug. Concrete walls a foot thick will be reinforced with steel. There also will be fire hydrants in the trench — built flush with the surface.
DISPATCH TOM DODGE Walls are going up inside the trench as it’s being dug. Concrete walls a foot thick will be reinforced with steel. There also will be fire hydrants in the trench — built flush with the surface.
 ?? DISPATCH (ABOARD WBNS CHOPPER 10)
On the Web ?? BROOKE LAVALLEY An aerial view shows work on the trench that will carry northbound express traffic through the Rt. 23/I-270 interchang­e. The middle of the trench has yet to be dug.
DISPATCH (ABOARD WBNS CHOPPER 10) On the Web BROOKE LAVALLEY An aerial view shows work on the trench that will carry northbound express traffic through the Rt. 23/I-270 interchang­e. The middle of the trench has yet to be dug.
 ??  ??
 ??  ??

Newspapers in English

Newspapers from United States