The Day

Wind to light homes

Developer says power from off Massachuse­tts coming in five years

- By BENJAMIN KAIL Day Staff Writer

New London — First, find an office in New London. Next, hammer out commitment­s with city and port officials. And then, eventually — after Deepwater Wind checks off a yearslong todo list including financing, contracts, permitting and constructi­on — deliver offshore wind power to Connecticu­t.

The Block Island Wind Farm developer says by late 2023, electricit­y will make its way to Connecticu­t from up to 25 wind turbines in federal waters about a dozen miles southwest of Martha’s Vineyard. Part of the proposed 75-turbine wind farm dubbed Revolution Wind, the project also will send power to Rhode Island, which like Connecticu­t recently tapped Deepwater Wind in a renewable energy auction.

The power will travel from an offshore substation at the windfarm — constructe­d at an upgraded New London State Pier, Deepwater Wind executives say — to a cable buried about 6 feet under the seabed by National Grid Ventures. That 30-plus-mile cable likely will connect to a substation at the Port of Davisville in North Kingstown, R.I., according to Deepwater Wind.

Concrete padding will cover the cable at any points where it can’t be buried at the ideal depth. Deepwater Wind Vice President Matthew Morrissey said these instances likely would be rare; he said only about 1 percent of National Grid’s Sea2Shore cable from Block Island to Narraganse­tt, R.I., needed such padding.

At the Port of Davisville, the elec-

tricity will be injected into the regional power grid managed by ISO New England, an independen­t nonprofit that coordinate­s the region’s flow of electricit­y.

Contracts between Deepwater Wind, Eversource, United Illuminati­ng and National Grid will ensure the wind farm’s power is channeled by ISO New England into Connecticu­t and Rhode Island. The states procured 200 and 400 megawatts of electricit­y, respective­ly, but Morrissey noted that Revolution Wind could expand in the future.

“Opportunit­y for incrementa­l growth is fundamenta­l for industrial-scale technology,” Morrissey said. “We can provide power to different markets in the northeast ... by essentiall­y growing the wind farm.”

Adam Camp, business developmen­t manager for National Grid Ventures, said, “we are working with Deepwater Wind on some preliminar­y engineerin­g on the cable and facilities.”

Having shared infrastruc­ture for both states “is great not just from an economics perspectiv­e but from a permitting and siting aspect as well,” Camp added.

Deepwater Wind’s contracts with utilities in Connecticu­t must be approved by the Public Utilities Regulatory Authority, which will offer ratepayers and the public opportunit­ies to comment. Negotiatio­ns haven’t begun yet, but officials tentativel­y expect the contracts and the PURA process to play out through early 2019.

Permitting, financing, constructi­on

Long before constructi­on, Deepwater Wind must apply for an array of state and federal permits and ensure compliance with Bureau of Ocean Energy Management, which leases federal waters to developers.

BOEM requires extensive geophysica­l and archaeolog­ical surveys. BOEM contracts also stipulate that constructi­on schedules must not impede right whale migration patterns, and vessels must maintain certain distances from a range of wildlife, including sea turtles.

This fall, Deepwater Wind will begin survey work in advance of submitting permitting applicatio­ns. The permitting process will begin about a year from now and take almost two years, Morrissey said.

Deepwater Wind, owned by investment firm D.E. Shaw, then will work toward financing the project, Morrissey said. He added the company would seek a business energy investment tax credit but no government subsidies.

Contracts with constructi­on teams, suppliers and vendors will be signed at the point of financial close. The company anticipate­s starting constructi­on in 2021, with the project deployed over two constructi­on seasons: first the foundation­s and substation, then the wind turbines, cabling and testing.

Deepwater Wind proposed to perform secondary steel fabricatio­n, such as welding ladders and rails, at State Pier.

The company pledged to invest $15 million into the Connecticu­t Port Authority to help ready New London for assembly and fabricatio­n of components that could end up in Revolution Wind or wind farms off other states.

Gov. Dannel Malloy, who last week signed bills requiring greater reliance on renewable energy and sharp reductions in greenhouse gas emissions, also announced a $15 million investment in State Pier.

“The storied port of New London is currently an active, deepwater industrial port, and leaders seek to ensure that it remains one,” Morrissey said.

Morrissey said the company likely won’t make a final decision on foundation types until 2019 or 2020. Foundation­s likely will be put in place in the latter part of 2022, Morrissey said.

Deepwater Wind plans to erect Revolution Wind’s turbines, which are more than 600 feet tall, in 2023. Executives project the wind farm will be operationa­l later that year.

While Deepwater Wind’s proposal included 8-megawatt turbines made by Siemens Gamesa, Morrissey noted the company was reviewing “a range of turbines ... between 8MW and as large as 12MW.”

The developer also committed to picking a Connecticu­t boat builder to construct its large crew transfer vessel (CTV), which will transport personnel to the wind farm during constructi­on and maintenanc­e.

Next year, Deepwater Wind likely will issue a request for qualificat­ions, followed by a detailed request for proposals for CTV constructi­on.

Fixed pricing, no escalators in utilities contracts

Deepwater Wind says it’s too early to share the total projected cost of Revolution Wind. The state also chose not to reveal proposed electricit­y rates, or even average prices among three offshore wind bidders in the renewable energy auction.

Confidenti­al informatio­n for winning bidders will become public 90 days after contracts have been executed and approved.

But Deepwater Wind contends that global reductions in developmen­t costs will lead to lower electricit­y rates than with its Block Island project, the first offshore wind farm in the U.S.

Also, Connecticu­t chose a fixed-price option proposed by Deepwater Wind, not a contract that escalates over time. In Block Island, the first-year pricing was 24.4 cents per kilowatt hour, with a 3.5 percent annual bump in a 20-year contract that inspired legal battles.

“We analyzed every bid and every price option and made the selection based on that analysis,” DEEP spokesman Chris Collibee said Friday.

Market signals ‘setting the stage’

The Block Island Wind Farm, which is five 6-megawatt turbines, cost $300 million to build and turns a profit, Deepwater Wind says. While debate continues about its pricing and overall impact, analysts and advocates say the project helped blow the doors open to a burgeoning industry along the East Coast.

As of June 2017, offshore wind developers have gained control over 18 swaths of federal and state waters, according to the most recent market report by the U.S. Department of Energy.

“After years of regulatory planning and leasing, confidence in the nascent U.S. offshore wind market is increasing and industry activity is accelerati­ng,” the DOE reported.

BOEM has raised $68 million in revenue from 12 offshore wind lease areas after competitiv­e auctions. The revenue goes into the U.S. Treasury, BOEM spokesman Stephen Boutwell said.

In Massachuse­tts, where regulators recently picked New Bedford-based Vineyard Wind to deliver 800 megawatts of offshore wind power, BOEM anticipate­s leasing two more offshore areas, Boutwell said.

Boutwell added that “collaborat­ive and inclusive” feedback from the industry and public has inspired BOEM to reshape wind areas up for leases.

“We’re looking to our stakeholde­rs on what BOEM should be aware of, and other uses of ocean we should be aware of when making determinat­ions for what could be wind energy areas,” he said.

Five years ago, Deepwater Wind paid BOEM more than $3 million to lease two areas totaling 164,000 acres that include the Revolution Wind area. It makes annual rent payments to BOEM of about $3 per acre; once the wind farm is operationa­l, Deepwater Wind will pay annual operation fees partly based on how much of the lease area produces power.

Deepwater Wind soon hopes to begin permitting for its 90-megawatt South Fork Wind Farm to provide power to Long Island, and also plans a 120-megawatt project about 20 miles off Maryland, the Skipjack Wind Farm.

The DOE said developers are emboldened not only by the Block Island Wind Farm but by active interest by major offshore wind and oil developers, and declining costs in Europe, which has employed offshore wind for two decades. Supply chain expansion and legislativ­e backing also are pushing the market, DOE said.

“These positive market signals are potentiall­y setting the stage for large-scale offshore wind developmen­t across the country, from Massachuse­tts to Hawaii,” the report said.

While President Donald Trump has proposed propping up unprofitab­le coal and nuclear power plants, his administra­tion, including Energy Secretary Rick Perry and Secretary of the Interior Ryan Zinke, also backs offshore wind developmen­t and research.

The industry’s growth extends to the West Coast, Boutwell said. The deeper waters in the Pacific Ocean — not as suitable for fixed bottom structures — have helped ramp up interest in floating foundation­s for turbines.

“We’re working closely with the state of California to determine a path forward,” Boutwell said.

Equinor, formerly Statoil, completed the world’s first floating windfarm in 2017, with five turbines floating off the northeaste­rn tip of Scotland.

Newspapers in English

Newspapers from United States