The Denver Post

WAIT TIMES SLOWING DEVELOPMEN­T

Long waits to submit applicatio­ns and disorganiz­ed filing system delay constructi­on

- By Jesse Paul

Long wait times to submit building-permit applicatio­ns and a disorganiz­ed filing system are delaying developmen­t across Denver, an audit finds.

Long wait times to submit building-permit applicatio­ns and a disorganiz­ed filing system are delaying developmen­t across Denver, an audit has found.

The problem is especially vexing as a booming population has pushed constructi­on — and a demand for permits — into high gear, Denver Auditor Timothy O’Brien said.

People start lining up hours before the Department of Community Planning and Developmen­t opens to hand in plans for review, he said, and the agency should take steps to dramatical­ly improve efficiency.

“Imbalances in staff training and long wait times are holding up the business of growing and developing the City of Denver,” O’Brien said in a written statement Thursday.

The department says that improvemen­ts are already either completed or underway in response to the auditor’s report, including digital-submission systems that have begun to reduce the wait for those trying to file plans. It disagreed, however, with the notion that Denver’s developmen­t boom is any way being hampered by the hold ups.

“I think the people that may be waiting at our counter are being held up for the duration of their time the at counter,” planning department spokeswoma­n Andrea Burns said. “Developmen­t in Denver is happening. The actual reviews of the plans are not being held up. The delays — we’re talking about minutes or hours. We are not talking about days or weeks.”

Chief among the Denver Auditor’s Office findings were inefficien­cies in the permit intake process that caused an average wait time of more than an hour and a half for submission­s of building permits. When compared to reported wait times in Colorado Springs, San Diego and Aurora, the division exceeds the average of 30 to 45 minutes, the office said.

Additional­ly, the department lacks sufficient storage capacity for the significan­t number of constructi­on plans submitted as part of the permit process, the audit found.

That issue has resulted in no defined organizati­onal system and time wasted by staff searching for documents, according to the auditor, which released photos of plans and paperwork stacked up at the department.

“Auditors also found that although customer feedback is provided and tracked, there is little or no management process for addressing the issues from customers,” O’Brien’s office said in a news release. “Best practices, standardiz­ed by federal executive orders, have not been implemente­d.”

Mayor Michael Hancock, who had not yet seen the audit, acknowledg­ed a longstandi­ng problem due to Denver’s rapid growth.

“We’ve seen an infusion of staff (and) we’ve seen changes in processes to get more efficient,” Hancock said. “Software has helped . ... But we can do much better. We recognize it — and I know CPD knows it, because I just left a meeting with them where this is all they talked about. We’re working on it.”

Burns said wait times have already been reduced since the building department began allowing online submission of permit applicatio­ns for small projects — like appliance installati­on and roof work — earlier this summer.

“We have a new queuing system going live within the month that will allow for people to make appointmen­ts to log in their plans for permits,” she said.

Before the end of 2018, the department hopes to allow all building permits — for any size project — to be submitted electronic­ally.

O’Brien says the planning department, which has seen historic levels of permit demand in the past several years, has also agreed to address the long lines by better training its staff by the end of 2018.

Burns emphasized that while there may be wait times for people trying to submit their plans for permitting, the actual review of those plans is going smoothly.

For new homes or additions of 400 square feet or larger and major commercial projects, it takes a month for the reviews to be completed. Intermedia­te residentia­l projects take two weeks for review.

“If you submit your plans for review, you will get them back within the time that we have promised you,” she said. “That is something we’ve achieved for the first time in a couple of years.”