The Denver Post

Issue could delay project

Concrete strength problem may mean 10-month setback in constructi­on at terminal

- By Jon Murray

Testing showing weaker-thanexpect­ed concrete in the main floor of Denver Internatio­nal Airport’s terminal has slowed constructi­on on a massive renovation project and could delay completion by up to 10 months, according to a new report produced by the contractin­g team.

The extent of the delay — and the severity of problems with the 25-year-old structure’s original concrete — won’t be known until at least April, DIA spokespers­on Stacey Stegman said. That’s when intensive testing of the concrete that is now underway is expected to be complete.

DIA expects that testing will shed light on the concrete’s loadbearin­g ability before contractor­s bring cranes onto the main floor of the terminal and begin erecting steel.

But a preliminar­y estimate by Great Hall Partners, the private consortium carrying out the $650 million renovation project, is that the concrete issues could delay the project by 209 work days.

That would equate to roughly 300 days when weekends and holidays are added in — or nearly 10 months beyond late 2021, the original target for completion.

DIA and the contractin­g team

say work is continuing on other parts of the project, but the delays affect a walled-off portion of the lower level beneath the airport’s tented roof. It’s the same main floor that includes the two main security checkpoint­s.

The contractin­g team, led by Madrid-based Ferrovial Airports and Centennial-based Saunders Constructi­on, disclosed the potential delay due to the concrete problems in a monthly project report filed on Thursday. That report was first covered by CBS4.

“The projected schedule represents their estimates but does not include the airport’s review and analysis or ways to mitigate” the problem, said Stegman, DIA’s vice president of communicat­ions, in a statement. “The issue cannot be fully known or realized until April when the testing is completed and the airport is able to review and analyze the results with Great Hall Partners.”

It’s possible, she said, that adjustment­s to project plans or constructi­on will be required, but engineerin­g experts “have informed us that the airport is safe and can support the constructi­on.”

Attempts to reach a spokespers­on for Great Hall Partners on Monday evening were not successful.

The root of the issue, according to both DIA and the Great Hall Partners report, was that the “compressiv­e strength” of the concrete, or its ability to bear heavy loads, was found in early testing last fall to be lower than what the airport’s project plans specified. Stegman said the inconsiste­ncy with plans “isn’t uncommon” in such a large project — but it has paused some work until it the problem’s full extent is known.

Another issue on the radar is the potential for deteriorat­ion within the concrete, which caused the replacemen­t of concrete in a DIA runway more than a decade ago. But Stegman said recent testing of concrete samples from the terminal “show no indication” that deteriorat­ion has occurred.

The renovation is part of a $1.8 billion public-private partnershi­p deal with the Ferrovial team that also covers three decades of private oversight of expanded terminal concession­s.

As part of the contract, Ferrovial agreed to a set cost for the renovation project, but with a big caveat: new requiremen­ts imposed by DIA and unforeseen constructi­on challeng- es were to be covered by a $120 million contingenc­y fund filled by the airport.

A recent accounting provided to The Denver Post by DIA shows that it has approved $7.2 million in additional costs, leaving a $112.8 million balance in that fund.

Work began last summer, and significan­t change is planned for much of the terminal. By the end of the project, the main floor security will move upstairs to expanded spaces on the north ends of each side of the terminal. Consolidat­ed airline check-in areas that occupied the length of the upper floor are being consolidat­ed in the south and middle portions of that level.

Downstairs, the south end of the main floor will become a welcome plaza. The north end will have new shops and other concession­s that are walled off in a secure area that travelers will pass through as they descend from the new security checkpoint­s to the undergroun­d train that goes to the concourses.

Newspapers in English

Newspapers from United States