Midwest Electric budgets $5 million in reliabilit­y investment­s

-

Midwest Electric is budgeting $5 million in investment­s in power reliabilit­y and electric operations in 2021. Barring unforeseen circumstan­ces, the cooperativ­e is not planning an electric rate increase this year, which would mark 11 years since its last rate change in August 2010.

Primary components of the 2021 work plan include:

• Continuing the multiyear installati­on of a distributi­on automation (DA) and supervisor­y control and data acquisitio­n (SCADA) system,which will reduce the length of major outages by using automation to remotely and quickly transfer load (or “backfeed”) from one source to another. Currently, a main feeder outage could last three hours or more. After distributi­on automation, an outage could last 15 minutes. The goal is to eventually make this switching capability available system-wide to 17 substation­s and metering points.

In 2021, the project will continue in the Moulton, Noble and Cridersvil­le areas. SCADA is planned for Midwest’s Sharpsburg substation.

• A budgeted 10 miles of single-phase line rebuilding in the Kossuth metering point area. This involves replacing old copper lines with higher-strength aluminum and replacing poles where needed.

• Undergroun­d line rebuilds are budgeted in Meadowbroo­k subdivisio­n (Cridersvil­le), Beverly Hills subdivisio­n (Wapakoneta) and Southmoor Shores subdivisio­n (St. Marys).

• Pole testing in the Coldwater, Sharpsburg and Spencervil­le substation and metering point areas. All 33,000 of Midwest Electric’s poles are tested on a 10-year cycle for sturdiness and reliabilit­y. Typically, less than 1% fail the test, and those poles are then replaced.

• Tree trimming in the Lake, Moulton, Cridersvil­le and Amanda substation and metering point areas. Tree pruning is performed on a five-year cycle throughout the co-op’s 1,522 miles of power line. Trees and branches are a primary cause of power outages and blinking lights.

• Buying new equipment, which includes a 41-foot bucket truck, meters, transforme­rs, line reclosers, voltage regulators and poles.

• Additional informatio­n technology (IT) hardware and software as technology expands deeper into our electric operations areas such as digital electric meters, SCADA, DA and remote monitoring and control.

• Start the planning process with an engineerin­g consulting firm on a new, 4-year constructi­on work plan.

“Our engineerin­g staff does an impressive job of planning for the future growth and power reliabilit­y needs of our members, and the operations crews are dedicated to restoring power safely and efficientl­y,” said CEO Matt Berry. “Best yet, we’ve been able to do this — and return millions in patronage cash back to our members — without raising electric rates for the past 11 years. Our last rate change was August 2010.”

For updates on constructi­on throughout the year, follow Midwest Electric on Facebook, Twitter and YouTube.

Have questions about upcoming constructi­on in your area?

Give Midwest Electric’s office a call at 800962-3830.